1963
In 1963 the City Planning Commission authorized a master plan for the Pacific Medical Center, drawn up by Skidmore, Owings & Merrill, under which the dental school and research building at Clay and Webster Streets were built.
-
March 6, 1969
The Pacific Medical Center, a teaching hospital known for heart surgery and mental health services, occupied buildings vacated by Stanford University on a site used for medical purposes for about 87 years. The City Planning Commission approved in part, with conditions, the Pacific Medical Center's request: final plans for a first-stage 311-bed hospital (expandable to about 500 beds, eight storeys and 155 feet above Buchanan Street) partly over Clay Street, an enlarged campus boundary, and a 400-car garage, subject to staff height and siting guidelines for a revised master plan.
-
1970s
Designed by Roslyn Lindheim, a leading figure in the design of modern healthcare buildings and founder of Planetree, whose work sought healthier and more humane settings for people in institutional care.
-
September 2, 1971
The Pacific Medical Center comprised a 250-bed hospital, research and teaching buildings, a dental school and a medical library; a new 311-bed hospital was under construction and a 395-car garage at Webster and Clay Streets had been completed.
-
September 30, 1971
On the Pacific Medical Center site, around the former Clay Street right of way between Webster and Buchanan Streets, a six-floor, 311-bed hospital was under construction, engineered for two further floors, beside an existing 95-foot dental building. The City Planning Commission voted 6-1 to approve, with conditions, a master plan for expanding Pacific Medical Center to a 500-bed teaching hospital, including height limits on several buildings and two floors removed from building H-2.
-
1972
Built.
-
June 15, 1972
The City Planning Commission approved, by 6-1 and with five conditions, the final preliminary plans for the first phase of the Pacific Medical Center professional office building: six floors of clinic and office space over a 210-space garage opposite Clay and Buchanan Streets, with no building permit until a revocable permit for traffic controls on Buchanan and Clay Streets was approved.
-
May 26, 1977
Only six floors of the Pacific Medical Center's main hospital building had been built of the eight the City Planning Commission authorised in 1971 (Resolution 6759); its institutional master plan was heard this day.
-
Nov 2011
6th floor & roof - renovate existing acu to add 4 recovery beds in out-patient ambulatory care unit - involves partitions, ceilings, casework, hvac, plumbing.
-
Mar 2012
6th floor & basement -renovate existing ies for a procedure room, patient toilet & staff locker/toilet room involves partitions, ceiling, hvac, plumbing, & electrical. add electrical equipment in the basement.
-
Oct 2012
Install electrical panel, special purpose receptacel, 1-phase branch circuits in existing new data closet on each floor with assoc it rack & anchorage on most floors. build 2 new data closets into storage rms in 2nd & 4th floor. provide a new groudning bar in new closet. install hvac unit on roof supply chelle.
-
May 2013
Stes: 512 & 514: remodel of existing clinic, selective removal of existing parttions, finishes, case work, ceilings, etc. insulation of new non rated partitions, casework, doors and finishes. mep under seperate permit. sprinklers and alarm under seperate permit.
-
Jan 2016
Voluntary access barrier removal, remodel doors in acccessible path of travel, replace & provide new accessible signage, remodel public toilets on all floors, add cane detection crossbars @ drinking fountains & exterior standpipe, striping at stairs, parking striping, new handrails at ramp.
-
Oct 2016
1/f & 4/f- voluntary access barriers removal, provide accessible signs, remodel exam. rooms & offices #104, 114, 115, 116, 151 to be fully accessible, remodel unisex toilet room 119 to be fully accessible, remove barries to access with floor office, modify sacremento street entrance & registration count.
-
Nov 2017
Renovate an existing shelled space to create an inpatient pharmacy to support 1st floor cancer infusion. all work on 5th floor.
-
May 2018
G/f: renovate an existing conference room and toilet room into an outpatient infusion suite and new single occupancy toilet room. the remainder of the existing infusion department will be paint, have 3 new sinks added and a door removed such that 2 rooms may be completely separated. life safety def.
-
Mar 2019
2nd fl: selective demolition and partial ti. work includes: new acessible toilet roomsl new partitions, ceilings and finishes; associated modifcation to existing poweder/data, lighting and existing hvac; new roof mounted condensing units. mep under seperate permit.
-
Mar 2019
Floors 1, 4 & 5 - selective demolition minor ti work on portions of floors. new non-bearing partitions, ceilings, finishes. floors 2 & 3 limited hardware changes. barrier removal under permit application 201511182992. new accessible toilets. mep included.
-
Mar 2019
5th floor: t.i. of cosmetic srgery/ breast surgery clinic. work included new accessible toilet rooms. idf room, partitions, ceiling and finishes, new power data, lighting and hvac.
-
May 2019
Stanford building 6: demolish (e0 dressing room. demolition existing handwash sink.build new dressing rooms ( one accessible): install one accessible sink and casework. add furring and acoustical wall to reading room. replace flooring and paint.
-
Mar 2020
Bpa #2019-0312-5023. fire alarm tenant improvement on existing spectronix mx fire alarm system. adding 77 chime strobe, 3 duct detector, 12 smoke detector, 2 power supplies and 1 door holder relay.
-
Aug 2020
Reroofing. commercial reroofing, tearoff built-up roof. install gaf everguar 80 mil tpo roofing system. 8, 140 sq ft. class a.
-
Oct 2022
Remodel of existing linear accelerator and control room.replace of existing linear accelelatro equipment.staff toilet room upgrade. this is an osphd 3 building.
-
Mar 2024
Lvl 1: selective demolition & partial t.i.: new accessible toilet rm. new partitions, ceilings & finishes. associated modification to e) power/ data, lighting & e) plumbing to save new department layout.
-
Sep 2024
Rooftop air cooler chiller replacement.
-
Oct 2024
Level 1: fire alarm ti: adding 1 power supply, 1 relay, 17 strobes and 11 horn strobes to existing spectronics mx addressable fire alarm system, 36 smoke detector are being replaced with new and in kind. ref ti permit 202403198157.
-
Mar 2026
Level 00: tenant space build out for urgent care space. work includes new partitions, doors, restrooms, archorage for equipment, and finishes. mep included.
DBI holds 171 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 171. 40 of them are nominal $1 street-space or sidewalk permits. 6 expired or cancelled permits are not shown.
Nearby
- 2250 Buchanan Street Same street
- 2400 Buchanan Street Same street
- 2230 Sacramento Street Around the corner
- 2323 Sacramento Street Around the corner
- 2329 Sacramento Street Around the corner