37.7647, −122.3945 A locator map appears here once a Mapbox token is configured.
Know This Place

District 10 · Block 3987, Lot 007 · ZIP 94107

135 Mississippi Street

Office building

  • 4 stories
  • 28,454 ft2
  • 9,544.5 ft2 lot area
  • 2 residential units
  • 3 rooms
  • 6 bathrooms
  • Zoned UMU
  • Historic resource
  • Sold May 20, 2021
37.7647, −122.3945 Street View appears here once a Google Maps embed key is configured.
  1. 1927

    Built as an industrial building, recorded as occupied by Reed Candy. Built by O'Brien Brothers. The survey is unsure between the builders O’Brien Brothers and Wilbur E. Puegh.

    Showplace Square / Northeast Mission Historic Resource Survey, adopted 2011
  2. June 3, 1971

    A three-storey poured-concrete building, equipped with a sprinkler system, covered the entire site. The City Planning Commission approved, with seven conditions, automobile dismantling and used-parts storage entirely inside the existing three-storey concrete building.

    San Francisco City Planning Commission minutes, San Francisco Public Library (Internet Archive)
  3. 1982

    Rehabilitated.

    Showplace Square / Northeast Mission Historic Resource Survey, adopted 2011
  4. Mar 1982
    Permit 8201967 $$$ $35,000

    Additions alterations or repairs.

  5. May 1982
    Permit 8204304 $$$ $135,000

    Additions alterations or repairs.

  6. Apr 2002
    Permit 200204164096 $$$ $125,000

    Alter 1 & 2/fl includes install new partitions/ltg/mechanical changes, modify sprinkler & access improve.

  7. Feb 2006
    Permit 200602275468 $$$ $105,000

    Tenant improvement of existing office including minor drywall work, interior storefront. installation carpet, minor electrical & plumbing to accommodate acessibility upgrades. no exterior work.

  8. Mar 2007
    Permit 200703237057 $$$ $105,000

    Tenant improvement to existing office space including minor dry wall work, electrical work and construction of new ada compliant unisex shower with plumbing; infill stair communicating between 2nd and 3rd floor (not an exit stair).

  9. Jun 2010
    Permit 201006184835 $$$ $80,000

    Site #sf53450a -installation of an unmaned telecomumications facility consisting of rooftop mounted equipment cabinets & antennas mounted to an existing penthhouse structure, concealed within new frp antenna boxes.

  10. Sep 2012
    Permit 201209058989 $$$ $120,000

    Barrier removal only, replace and restripe parking lot to provide compliant disabled access parking. remodel existing restrooms and provide power assist door control hardware at building entrance.

  11. Feb 2013
    Permit 201302119954 $$$ $125,000

    Structural only. remove wood framed structural columsn and floor framing. replace removed 2nd floor with new concrete slab, new structural steel framing on corresponding footings. exterior walls to remain.

  12. Mar 2013
    Permit 201303283290 $$$ $625,000

    Replace 3 exisitng non-forming stairs with 2 new required compliant egress stairs.

  13. Apr 2013
    Permit 201304225145 $$$ $388,500

    Remodel of existing office building, 3rd fl tenant improvement. mep, fire alarm & sprinkler under separate permit. ref permit application 201209058989.

  14. Apr 2013
    Permit 201304245329 $$$ $485,625

    1st floor-remodel of existing 1st floor office, open office areas, meeting rooms, training rooms. m.e.p, sprinkler, fire alarm under seperate permit.

  15. Apr 2013
    Permit 201304305800 $$$ $198,300

    2nd floor-remodel of existing office. m.e.p, sprinkler, fire alarm on seperate permits.

  16. May 2013
    Permit 201305308244 $$$ $486,000

    Exterior improvements including new deck and new mechanical equipment lift on 6' columns. replace 3 windows with new roll up window/doors. ugrade 2 exit doors.no interior work.

  17. Jul 2013
    Permit 201307091421 $$$ $75,000

    Demolition and relocate new partitions on 2nd floor.

  18. Jul 2013
    Permit 201307172075 $$$ $110,000

    Existing fire sprinkler system. t.i.: removed 345 sprinklers. added (changes out) 335 sprinklers at 1st, 2nd, and 3rd floors.

  19. Nov 2020
    Permit 202011108613 $$$ $156,041

    Reroofing. tear off existing bur, install firestone tpo single ply above 2" insulation with 1/4" coverboard, new counter flashings.

  20. Sep 2021
    Permit 202109087915 $$$ $1,000,000

    3rd fl t.i.- existing 3-story type ii office building to office use on 3rd fl. scope of work is limited to interior alteration, minor site work & upgrade to infrastructure. the building evelope is not impacted. mep, sprinklers and fire alarm deferred.

  21. Sep 2021
    Permit 202109299425 $$$ $2,500,000

    1st floor ti permit - architectural tenant improvement of 1st floor of an existing three story type ii-b office building to office and lab use on first floor. scope of work is limited to interior alterations, minor site work, and upgrades to infrastructure. the building envelope is not impacted.

  22. Sep 2021
    Permit 202109299432 $$$ $2,500,000

    2nd floor ti permit - architectural tenant improvement of 2nd floor of an existing three story type ii-b office building to lab use on second floor. scope of work is limited to interior alterations, minor site work, and upgrades to infrastructure. the building envelope is not impacted.

  23. Apr 2022
    Permit 202204212716 $$$ $100,000

    Per ab-017, soft demolition for 1st & 2nd fl of an existing 2-story type ii-b office building. no structural work under this permit. no construction under this permit. building envelope is not impected. ref fire sprinkler permit application 202204071756. ref ti #202109299425 & 202109299432.

  24. May 2022

    Mechanical, electrical & plumbing improvements. deferred from permit application 202109087915. ** maher: n/a ** no mechanical work or electrical work on roof under this permit. no site electrical or plumbing work.

  25. Sep 2022

    Owner improvements to existing parking lot including upgrade to trash enclosure, entrance gate and accessible parking space. site work associated with permit application 202109299425 & 202109299432.

  26. Feb 2023
    Permit 202302021289 $$$ $416,000

    1st fl & mezzanine defered mep for permit application 202109299425.

  27. Feb 2023
    Permit 202302021291 $$$ $5,000

    2nd fl deferred mep for 202109299432.

DBI holds 79 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 79. 1 of them are nominal $1 street-space or sidewalk permits. 1 expired permit is not shown. The statement's narrative dates the warehouse to 1925; the survey data table gives 1927.