329–333 Brannan Street
Office building
-
Jun 2013
To erect 6 stories, 1 basement, (commercial) office, retail & parking building.
-
Sep 2013
Demolish one story workshop & office. (building# 1) maher: compliance with ordinance no. 155-13 not required. see attached.
-
Oct 2013
Excavation shoring for new development on 333 brannan st. (reference permit application 201306280744-s).
-
Oct 2013
Shoring & tieback to allow excavation for new development on 333 brannan st. (ref permit application 201306280744-s).
-
Feb 2014
Erect free standing tower crane to be used in building construction. ref #2013.0628.0744. n/a for the maher ordinance #155-13.
-
Sep 2014
Added communicating openings with 345 brannan & ab 010 form; revised 333 building facade @ property line to coordinate with 345 brannan expansion joint. base building electrical room moved from roof to 5th fl. ramp, stair & egress path changed @ courtyard. change to roof landscape design & lighting. adjustment to.
-
2015
Current structure built.
-
Oct 2015
Lower terrace parking level sub ground floor to build new partitions, doors, millwork, ceilings and mep. n/a for maher. mechanical/plumbing assembly in building on 3/f only; electrical, life safety, sprinklers uder separate permit.
-
Oct 2015
Ti on 1st floor to build new partition doors, finishes, millwork and food service, mep on separate permit.
-
Oct 2015
3rd floor ti- build new partitions, doors, millwork, finishes and ceilings. maher na. mep, life safety and sprinklers under separate permit.
-
Oct 2015
2nd, 4th, 5th floor - construction of new partitions, doors, millwork, ceilings & finishes. life safety, sprinklers & mep under separate permit. n/a maher ordinance.
-
Nov 2015
Mechanical, electrical & plumbing for floors 2, 4, 5 to install new equipment & fixture throughout. see appln #201510270924 for reference.
-
Dec 2015
Fire sprinkler ti on 2nd, 4th and 5th floors, ref pa 2015-1027-0924. add 371 heads & relocate 84, total 455 heads. maher na.
-
Dec 2015
3rd floor: t-24 lighting and power for 3rd floor t.i. ref. permit application 201510210423 for architectural work; maher n/a.
-
Jan 2016
Install t-24 mechanical equipment on roof to facilitate food service equipment on 3rd fl. & roof, see permit application 201510058804 for struc footing and 201510210423 for 3rd fl food service equip and architectural. compliance with maher ordinance no 155-13 not required.
-
Jan 2016
1st floor - title 24 mep to install new equipment on floor t.i. refer to permit application 201510200250. n/a maher ordinance.
-
Jan 2016
Under terrace - title 24 lighting to install new fixtures & outlets on lower terrace level. refer to permit application 201510087231. n/a maher ordinance.
-
Mar 2016
Install optional standby diesel generator on the roof location of generator approved by planning via permit application 2016/02/29/0775. ** maher: n/a **.
-
Apr 2016
Restaurant build out of an exisitng shell. indoor & outdoor dining areas, bar, kitchen, food/beverage storage & bathrooms. including but not limited to built-in furniture & interior walls & finishes.new hood & duct & air /maid bleed of system n/a for maher ordinance no. 155-13.
-
Jul 2016
Errcs-emergency radio responder coverage system for 5 story building. ** maher: n/a **.
-
Oct 2017
3rd floor - demolition of non-structural partitions, dfh, casework & lighting. construction of non-structural partitions, dfh, casework & lighting. deferrred submittals - mep, fire, life safety. ada improvements. n/a maher ordinance.
-
Nov 2017
3rd floor: mechanical & ele title 24 upgrade mechanical system lighting and power. no exterior work. floor is currently occupied. ref 201710242075 - for ti work maher na.
-
Aug 2019
Basement and 1/f & basement - demolition on non-structural partition walls & door, frame and hardware. new non-structural partition wall with counter.
-
Jan 2022
Installation of charging infrastructure for plug-in hybrid electric vehicle chargers. not for public use.
-
Jul 2022
Repalce existing fire pump with like in kind demolition existing parking garage system to be repalced with new extra hazard 2 occupancy for ev charging protection tie in remaining existing system to preserve system integrity (basement) job 22-651 ref 2022-0114-6035.
-
August 28, 2026
Exclusive: New AI start-up with ‘extreme’ work culture takes over S.F. office abandoned by Cruise — San Francisco Chronicle
DBI holds 72 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 72. 8 of them are nominal $1 street-space or sidewalk permits. 1 expired permit is not shown.
Nearby
- 326 Brannan Street Same street
- 334 Brannan Street Same street
- 345 Brannan Street Same block
- 355 Brannan Street Same block
- 301 Brannan Street Same block
- 640 Second Street Same block
- 98 Jack London Alley Around the corner
- 35 South Park Around the corner