329–333 Brannan Street
South Beach · San Francisco, CA 94107
Permit history
-
Jan 2003
Reroofing.
-
Jun 2013
To erect 6 stories, 1 basement, (commercial) office, retail & parking building.
-
Sep 2013
Demolish one story workshop & office. (building# 1) maher: compliance with ordinance no. 155-13 not required. see attached.
-
Oct 2013
Excavation shoring for new development on 333 brannan st. (reference permit application 201306280744-s).
-
Oct 2013
Shoring & tieback to allow excavation for new development on 333 brannan st. (ref permit application 201306280744-s).
-
Feb 2014
Erect free standing tower crane to be used in building construction. ref #2013.0628.0744. n/a for the maher ordinance #155-13.
-
Sep 2014
Added communicating openings with 345 brannan & ab 010 form; revised 333 building facade @ property line to coordinate with 345 brannan expansion joint. base building electrical room moved from roof to 5th fl. ramp, stair & egress path changed @ courtyard. change to roof landscape design & lighting. adjustment to.
-
Oct 2015
Lower terrace parking level sub ground floor to build new partitions, doors, millwork, ceilings and mep. n/a for maher. mechanical/plumbing assembly in building on 3/f only; electrical, life safety, sprinklers uder separate permit.
-
Oct 2015
Ti on 1st floor to build new partition doors, finishes, millwork and food service, mep on separate permit.
-
Oct 2015
3rd floor ti- build new partitions, doors, millwork, finishes and ceilings. maher na. mep, life safety and sprinklers under separate permit.
-
Oct 2015
2nd, 4th, 5th floor - construction of new partitions, doors, millwork, ceilings & finishes. life safety, sprinklers & mep under separate permit. n/a maher ordinance.
-
Nov 2015
Mechanical, electrical & plumbing for floors 2, 4, 5 to install new equipment & fixture throughout. see appln #201510270924 for reference.
-
Dec 2015
Fire sprinkler ti on 2nd, 4th and 5th floors, ref pa 2015-1027-0924. add 371 heads & relocate 84, total 455 heads. maher na.
-
Dec 2015
3rd floor: t-24 lighting and power for 3rd floor t.i. ref. permit application 201510210423 for architectural work; maher n/a.
-
Jan 2016
Install t-24 mechanical equipment on roof to facilitate food service equipment on 3rd fl. & roof, see permit application 201510058804 for struc footing and 201510210423 for 3rd fl food service equip and architectural. compliance with maher ordinance no 155-13 not required.
-
Jan 2016
1st floor - title 24 mep to install new equipment on floor t.i. refer to permit application 201510200250. n/a maher ordinance.
-
Jan 2016
Under terrace - title 24 lighting to install new fixtures & outlets on lower terrace level. refer to permit application 201510087231. n/a maher ordinance.
-
Mar 2016
Install optional standby diesel generator on the roof location of generator approved by planning via permit application 2016/02/29/0775. ** maher: n/a **.
-
Apr 2016
Restaurant build out of an exisitng shell. indoor & outdoor dining areas, bar, kitchen, food/beverage storage & bathrooms. including but not limited to built-in furniture & interior walls & finishes.new hood & duct & air /maid bleed of system n/a for maher ordinance no. 155-13.
-
Jul 2016
Errcs-emergency radio responder coverage system for 5 story building. ** maher: n/a **.
-
Oct 2017
3rd floor - demolition of non-structural partitions, dfh, casework & lighting. construction of non-structural partitions, dfh, casework & lighting. deferrred submittals - mep, fire, life safety. ada improvements. n/a maher ordinance.
-
Nov 2017
3rd floor: mechanical & ele title 24 upgrade mechanical system lighting and power. no exterior work. floor is currently occupied. ref 201710242075 - for ti work maher na.
-
Aug 2019
Basement and 1/f & basement - demolition on non-structural partition walls & door, frame and hardware. new non-structural partition wall with counter.
-
Jan 2022
Installation of charging infrastructure for plug-in hybrid electric vehicle chargers. not for public use.
-
Jul 2022
Repalce existing fire pump with like in kind demolition existing parking garage system to be repalced with new extra hazard 2 occupancy for ev charging protection tie in remaining existing system to preserve system integrity (basement) job 22-651 ref 2022-0114-6035.
DBI holds 72 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 72. 8 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update