37.7895, −122.3901 A locator map appears here once a Mapbox token is configured.
Know This Place

District 6 · Block 3744, Lot 003 · ZIP 94105

Hills Plaza

345 Spear Street

  • Office building
  • 7 stories
  • 426,760 ft2
  • 89,231 ft2 lot area
  • Zoned M1
  • Sold August 12, 2004
37.7895, −122.3901 Street View appears here once a Google Maps embed key is configured.
  1. 1990

    Built.

  2. Sep 2005
    Permit 200509223550 $$$ $150,000

    Oti-2 6/f el, me, ls.

  3. May 2007
    Permit 200705252302 $$$ $1,500,000

    Oti-1, google, 4th floor, el, me, ls, sp.

  4. Jul 2007
    Permit 200707096265 $$$ $1,000,000

    Full floor mechanical and electrical work. ref #200705252302.

  5. Oct 2007
    Permit 200710155420 $$$ $1,108,000

    2nd. floor tenant improvement. t.i. remodel existing vacant space. build new walls for office and conference rooms. relocate existing lights, existing ceiling grid & tile to remain, patch as req'd. hvac, fire sprinkler, life safety, electrical., under separate permits.

  6. Dec 2008
    Permit 200812168547 $$$ $1,105,600

    Fire alarm system upgrade. install 3 addt'l nodes (fcc room already complete) out of 4. new smoke control panel and new devices on floors: b-2, b-1, ground, 5, 6, 7, 8 and 8 thru 18. also connect common garage devices (33 sprinkler/strobes) @ 2 harrison street.

  7. Aug 2011
    Permit 201108172661 $$$ $1,815,580

    Interior alteration for offices on floor 6 including drywall, ceilings, demolition, doors, millwork and finishes. mep under separate permit.

  8. Aug 2011
    Permit 201108293459 $$$ $1,376,075

    6th floor-interior t.i. including new drywall, ceilings, doors, frames, glazing, millwork & finishes. mechanical, electrical, lighting, sprinklers & life safety under seperate permit.

  9. May 2014
    Issued Permit 201405135585 $$$ $3,000,000

    Tenant improvement on the 5th fl. new partitions, willwork, finishes. associated mep and sprinklers and life safety under separate permit.

  10. May 2014
    Permit 201405155855 $$$ $1,920,000

    5th floor: mechanical and electrical associated with approved app#201405135585 including new hvac and lighting. n/a for the maher ordinance #155-13.

  11. Jun 2014
    Permit 201406118144 $$$ $1,400,000

    Cafe 3rd floor: minor demolition, new wall, kitchen equipment and mechanical & electrical. installing new hortzontial exit. ls & sprinklers under seperate permit. n/a ordinance #155-13-per pre-application mtg 7-3-14- phase i- temp exiting corridor- sealing convience stair. occupant load.

  12. Aug 2014
    Permit 201408184059 $$$ $3,805,000

    T.i. on 3/f including new offices, conference rooms & restrooms. mechanical, electrical, fire alarm system & fire sprinkler system under seperate permit. n/a ordinance #155-13.

  13. Aug 2014
    Permit 201408254589 $$$ $1,700,000

    Mep work associated with approved permit #201408184059. n/a maher ordinance # 155-13.

  14. Jan 2015
    Permit 201501236545 $$$ $3,100,000

    7th floor: ti. include demolition, refurbishing of existing restrooms, new partitions & new ceilings. mep, fire alarm and sprinklers under separate permit. new occupant loads and pavers on roof. sffd assembly permit required.** maher: compliance with ordinance no# 155-13 not required **.

  15. Jul 2015
    Permit 201507020572 $$$ $3,980,000

    2nd floor: to include new b-occupancy conference rooms, fitness area, locker rooms, new bathrooms and new finishes thoughout. mechanical electrical and fire life safety is under seperate permit. n/a for maher.

  16. Jul 2015
    Issued Permit 201507020540 $$$ $1,513,000

    Lobby upgrades to finishes on level 1 and associated lighting for signage in the lobby. n/a for maer.

  17. Aug 2015
    Permit 201508063526 $$$ $1,450,000

    Mechanical and electrical work associated with 201507020572 including new lighting, new ductwork, and heat pumps.

  18. Jul 2017
    Permit 201707263017 $$$ $1,215,000

    6th floor remodel, existing tech talk room, conference rooms 9 fire doors.

  19. Mar 2019
    Issued Permit 201903114864 $$$ $2,800,000

    6th floor - construction of a new catering kitchen and office space. new grease trap that runs from the 5th flooor through the 7th fl. 8th fl and roof equipment included in scope. structural deferred for grease interceptors & 8th floor rooftop anchorage. n/a for maher.

  20. Jun 2020
    Permit 202006269187 $$$ $922,900

    Suite 120: tenant improvement-2800 sq ft medical abulatory care facility.

  21. Nov 2022
    Permit 202211287247 $$$ $2,100,000

    4/f: tenant improvement and structural to support demolition permit. new partitions, ceilings, fixtures, millwork and finishes. ref demolition permit 202211106283. mep deferred.

  22. Dec 2022
    Permit 202212198675 $$$ $5,000,000

    4th fl new non structural partitions, ceiling, light fixtures, millwork, finishes. no exterior work. mep deferred.

  23. Dec 2025
    Filed Permit 202512111594 $$$ $350,000

    Tenant improvement of first floor fitness space at hills plaza. tenant improvement includes construction of non-bearing partition, finishes, doors, frames, and hardware.

DBI holds 540 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 540. 18 of them are nominal $1 street-space or sidewalk permits. 3 expired or cancelled permits are not shown.