979–989 Market Street
South Of Market · San Francisco, CA 94103
-
1979
One of about sixty buildings in the Central SoMa study area given San Francisco Architectural Heritage's top two ratings in the Downtown Survey published as Splendid Survivors.
-
Mar 1982
Otc alterations permit.
-
Jul 1990
Seismic steel erection, architectiral alterations (interior).
-
Mar 1991
Cti i.
-
Apr 1991
Cti-1.
-
Apr 1991
Cti-1.
-
Apr 1991
Cti-1.
-
May 1991
Main lobby, storefront on grd. floor.--- express p/c.
-
Jul 1998
Oti 2 2nd floor/el, me.
-
Nov 1999
Oti-1 2nd floor el, me, l/s, sp.
-
Sep 2000
Tenant improvement.
-
May 2001
Oti-1 5th floor ltg mechanical ls spr.
-
May 2001
Oti-1 6th floor ltg mechanical ls spr.
-
Apr 2010
Ground floor retail tenant improvement. install new freight elevator and stairs to basement. install new accessible wheelchair lift to existing mezzanine. hvac & lighting under separate permit.
-
May 2011
Office ti on the 3rd fl. renovate. ofexisting conf rm to 1 conf rm and office. renovate of work rm into 3 offices, store rm to employer break rm. add 4 phone rooms.
-
Apr 2012
Interior non structural t.i. of the 6th floor. mep, fire safety under seperate permit.
-
May 2012
Interior tenant improvement on floors 4 and 5. all mep under separate permit.
-
May 2012
M.e.p. for floors 4 & 5-ti approved under app# 201205100245.
-
Jul 2013
Reroofing.
-
Aug 2018
4th floor. tenant improvement. demolition of non-structural partitions. new non-structural partitions ceilings, millwork with finishes. mep and fire life safety under separate permit. maher n/a.
-
Aug 2018
5th floor. tenant improvement. demolition of non-structural partitions. new non-structural partions ceilings, millwork with finishes. mep and fire life safety under separate permit. maher n/a.
-
Feb 2019
2nd floor. tenant improvement incl new partitions, new acoustical ceilings. mep, life safety & sprinkler under separate.
-
Mar 2019
T.i. improvement on the 6th fl. new non structureal partitions finishes, acoustical ceilings, mep & fire life safety under sep permit.
-
Apr 2019
2/f: mep for tenant improvement on the 2nd fl ref pa 2019-0207-2322.
-
Aug 2019
3rd floor: full floor t.i. to include non-structural partitions, new interior ceilings. new restrooms. mep, life safety, fire sprinkler under seperate permit. n/a for maher.
-
May 2024
Installation of steel channel to reinforce corroded column. west facade only was 100 percent tuckpointed.
DBI holds 213 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 213. 16 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the developer and the early tenants. Submit an update