Permit history
-
Aug 1984
Additions alterations or repairs.
-
Oct 1986
Exterior; cut new openings in brick walls.
-
Feb 1996
Cti-1 3rd fl el me sp.
-
Feb 1996
Cti-1 4th fl el me sp.
-
May 1996
Electrical work only.
-
Feb 1997
T/i on 2/f include new mens & womens toilet rooms.
-
Mar 1997
Cti-1 floor 1st el sp me.
-
Oct 2000
Underpinning per plan in conjunction with new const (2000-05-09-9478s).
-
Mar 2006
Add anchor bolts and wall ties confirming to table 16c-e (4) to substitute tension bolts installed under previous application for umb compliance in 1986 p/a 8613347.
-
Jul 2007
Project incl new improvements on g/f lobby and 2nd fl elveator lobby of an existing office building. work includes improvements floors, ceiling, walls and lighting.
-
Dec 2007
Internia tenent improvement including new walls at 3rd and 4th floors ceiling work, doors, and glazing, m.e under seperate permit.
-
Jan 2008
Reroofing. commericial reroofing (cool roof).
-
Jan 2008
Over lap roof with insulation and durolast 40 mil.
-
May 2008
Front facade improvement includes new storefront and canopy at the main building entrance. a new storefront to replace existing roll down door at a secondary entrace and new exterior lighting.
-
May 2008
Ground floor improvements, work includes new floor finishes & lighting; new rated enclosures at existing freight elevator shafts; new rear exit; reconfigured rear loading dock; and new space for tenant bicycle storage; new accessible restrooms. m.e.p. under separate permit.
-
Dec 2008
T.i. for ground floor - new floor finishes, electrical, lighting & mechanical, new acoustical enclosure at new shop, new workspace & project rooms. (all mep under separate permit).
-
Jul 2011
Tenant improvement on the 3rd floor including demolition & construction of interior partitions, ceiling electrical & finish work. mep under separate permit. sprinkler & life safety under separate permit.
-
Nov 2015
G/f -t.i. demolition of some existing partitions, a new full & partial height partitions, separate permit for electrical power/lighting distribution, mechanical system distribution, life safety system changes. and finishes. add 1 accessibe unisex convenience restroom in suite. sep mep.
-
Dec 2015
New lighting and branch circuting to exiting panel maintained some existing power and signal outlets and provided additional new power branch circuiting and reaceway systems as required to new power and outlets.
-
Jan 2017
2nd floor: minor ti - new non load bearing partitions, lighting & interior finishes, no exterior and no structural work maher na.
-
May 2018
New finishes millwork for showroom. structural - ceiling support for ceiling grid. new non-structural partition. new power receptacle, power and data.
-
Nov 2018
T.i to existing offices to incl new finishes at restrooms and kitchen areas with plumbing fixture replacement. 3rd and 4th floor only.
-
Aug 2022
T.i., collaboration space & break room. interior only, no change to existing use.
-
Dec 2022
Ground floor - new opening at existing brick wall. reloacation of existing electrical panel currently located at proposed new brick opening. removing gyp/mtl stud wall & associated doors @ existing brick opening. portion of new concrete infill wall to be gyp/mtl stud wall for potnetial future double doors.
-
Jun 2023
Interior office renovation at level 1, suite 110a/b, interior main lobby renovation, new interior walls, storefront glazing, finishes, doors, hardware, access control, millwork at break area, plumbing area, lighting controls, power/data outlet. ref: 202205265059. fire alarm/fire sprinklers deferred.
DBI holds 103 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 103. 5 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the developer, the early tenants and the date of the last recorded sale. Submit an update