1906
Built immediately after the earthquake as the Paul Wood Warehouse, beside the former Southern Pacific rail yard. It retains an extremely high level of architectural integrity, and was put forward for San Francisco Landmark designation.
-
Aug 1984
New construction.
-
Mar 1987
Floor to structure 1 hr partitioning with rated corridor dr.
-
Jun 1987
Floor to structure 1 hr partit. with ul rated corridor doors.
-
Feb 1991
Add new corridor with misc partitions on 5/f.
-
Jan 1996
Cti 1 5th floor el me sp.
-
Apr 1996
Cti-2 (el me sp) 5th fl.
-
Jan 1997
Cti-1 floor 4th architecture.
-
May 1997
Cti-2 (el me sp) 4th floor.
-
May 1997
New reception desk at existing lobby 180sf.
-
Aug 1997
Cti-1 floor 4th el sp me ls.
-
Sep 1997
Cti-2 floor 4th el me.
-
Sep 2000
Oti-1 3rd floor el, me, l/s, sp.
-
Sep 2000
Oti-1 5th floor me sp.
-
Oct 2000
Oti-1: el, me, sp (4th fl only).
-
Nov 2000
Convert lightwell concrete in fill #2 into conference rm framing drywall electric 4th fl taping pain.
-
Dec 2001
Installation of new fire alarm system on all floors.
-
Aug 2012
4th & 5th floor - convert portion of 5th floor b occupancy to a-3 occupancy for trianing, elimate rated corridor between offices & broadcast studios. the new a-3 "training room" shall be used by building employees only, and shall not be used by the general public.
-
Sep 2012
4th & 5th floors-tenant improvement fire sprinkler-add 70 sprinklers, relocate 17 sprinkler & plug 74 ssp's ti permit application 2012-0816-7560.
-
Oct 2012
4th and 5th floor: add 2 power supplies, 19 horn/strobes, 23 strobes and one horn, replace 14 existing horn/strobes and 1 strobe.
-
Aug 2020
Barrier removal permit to convert existing parking garage, and document planning motion 20523. at accessible parking spaces, provide new painting striping, code compliant symbols & signage, provide bike parking spaces. no exterior improvements. no mep or life safety. existing code compliant fire life safty.
-
Jul 2021
Renovatiaon of second generation commercial interior office work to include conjunction of new partions, finishes lighting and meps 5th fl.
-
Jul 2021
Soft demolition at level 5. remain vacancy under ab-017.
-
Aug 2021
Provide fire alarm ti on the 5th fl.
-
Feb 2022
Renovation of 2nd generation commerical interior office space. work includes structural reinforing as required by structural drawings. revisions to permit 202107134301 and 202107134269.