37.7869, −122.4138 A locator map appears here once a Mapbox token is configured.
Know This Place

District 3 · Block 0304, Lot 006 · ZIP 94102

630 Geary Street

Hotel

  • 5 stories
  • 15,925 ft2
  • 3,437.5 ft2 lot area
  • 54 residential units
  • 68 rooms
  • 20 bathrooms
  • Zoned RC-4
  • Historic resource
  • Sold June 1, 2020
37.7869, −122.4138 Street View appears here once a Google Maps embed key is configured.
  1. 1913

    Built.

  2. April 10, 1913

    Mutual Construction company contracted to put up a five-storey and basement reinforced concrete hotel, at $40,000. Cross streets: N line of Geary Street, 112:6 feet W of Jones.

    The San Francisco Call, 10 April 1913, p. 15
  3. November 15, 1913

    Going up as a hotel of 60 guest rooms and 10 private baths, with a lobby and lounge in front, dining rooms in the basement and a classic front in white cement with marble and tile trim, at $40,000; designed by Rousseau & Rousseau. Site as recorded: The north side of Geary Street west of Jones, lot 25 by 137 ft 6 in.

    The San Francisco Call, 15 November 1913, p. 8
  4. October 1971

    The Paul, a residential hotel, had 60 units, of which 7 were vacant.

    URS Research Company / Arthur D. Little, Inc., Yerba Buena Center Public Facilities and Private Development: Environmental Impact Report (draft), prepared for the City and County of San Francisco, 1973.
  5. Feb 1987
    Permit 8702279 $$$ $8,700

    To bring into code.

  6. Aug 1987
    Permit 8710972 $$$ $6,000

    Repair concrete parapet to conform to earthquake requirement.

  7. Dec 1988
    Permit 8820542 $$$ $250

    Hall ventilation fire damper in wall on first floor.

  8. Dec 2004
    Issued Permit 200412302342 $$$ $14,431

    Install new unimoole 200 fire control panel & fire protection devices on 1st floor. interface new pane.

  9. Jun 2010
    Permit 201006255274 $$$ $8,000

    Install 1 illuminated blade sign reading park for tower 737 on geary st elevation.

  10. Sep 2011
    Permit 201109305923 $$$ $15,000

    Legalize/remodel e kitchen and 2 1/2baths, and laundry room at basement. comply with complaint 20114611, 201143222. comply with his nov dated 7/25/11 comp 201147027.

  11. Oct 2011
    Permit 201110317996 $$$ $1,000

    Revision to appl #200305023700 to comply with fire sprinkler ordance, to comply with nov #201147027 -fire sprinkler ordance, (3) heads in garbage chute, (1) in basement, (1) on 2nd floor, (1) on 4th floor. (no plans).

  12. Nov 2011

    Renew permit #200405184213 for final inspection.

  13. Sep 2012

    Obtain final inspection for work approved under permit application 2003-0502-3700. all work is complete.

  14. Jun 2013
    Permit 201306139523 $$$ $3,780

    Comply with ordinance 029-13 only grab bars. basement: 4 in 2 baths. 1st fl: 6 in 3 baths, 2nd/3rd: 8 in 4 baths, 4/5th fl, 8 in 4 baths. 42 total.

  15. May 2014
    Permit 201405095413 $$$ $6,700

    Replace existing shower stalls with new shower stalls in the common bathrooms. 2 showers on each floor - floors 1-5 = 5 floors total.

  16. May 2019
    Issued Permit 201905231521 $$$ $800

    Remove abandoned abby hotel sign and all associated hardware. wall to be patched to match existing. no other work under this permit.

  17. Mar 2021
    Issued Permit 202103116398 $$$ $100,000

    Comply with nov 202173833 & 202173835. convertexisting basement entertainment rm tonew storage rm with full bath, convertexisting communal baths on floors 1-5 to new utility closets with janitorial sinks, 1/f reconfig/change use of 2existing rms to new ofc & restore kitchen to mgrs dwelling unit. convert 30existing guest rm.

  18. Apr 2022
    Issued Permit 202204122079 $$$ $10,000

    Like for like fire alarm system replacement. voluntary. replace facu, annunciator, smoke detectors, manual pull stations. install ars radio, monitor modules. addition devices will be installed in phase 2.

  19. Apr 2024

    To obtain final inspection for work approved under permit application 202007029508. all work is complete.

  20. Jun 2025
    Permit 202506138720 $$$ $10,000

    Replace/repair in kind: lubricate/ paint fire escape and acordian ladder, patch hole, clean remotar, and paint concrete walls where needed. clean, patch, and expoxy exposed rebar at nw corner at 5th fl and where needed. secure misaligned metal exhaust at roof level, recondition, clean/ paint window.

  21. Oct 2025
    Issued Permit 202510207705 $$$ $180,000

    Recommenecement and completion of work approved under 202103116398.

  22. Oct 2025
    Issued Permit 202510207708 $$$ $120,000

    Revision 202103116398- legalization of unpermitted kitchen relocation with in existing basement per 202173833 and 202173835.

  23. Dec 2025
    Issued Permit 202512030873 $$$ $700

    As built change log reference plan # 202204122079 per inspector comments. corrected floor plans to reflect what is on site basement area. added 1 horn strobe on basement in kitchen area.

DBI holds 27 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 27. 1 of them are nominal $1 street-space or sidewalk permits. 5 expired or cancelled permits are not shown.