1968
Woodside Gardens, designed by Neill Smith & Associates for the San Francisco Housing Authority — one of the few Brutalist large apartment buildings in the city. It has since been painted.
-
May 1987
Bring building into compliance required by dahi.
-
Jul 1993
Install emergency power generator including concrete pad.
-
May 1995
Removal of existingsmoke detectors & instal new smoke detectors.
-
Sep 2003
Demolition range&base cabinets at 24units & replace with free standing range&overhead cabinets.ductless hood.
-
Apr 2010
Installation of new fci e 3 fire alarm system with remote lcd and directory annuciators.
-
Jun 2011
Replace existing 150 kw deisel outdoor generator and automatic transfer switch with new. the existing generator has corroded and can not be fixed.
-
Mar 2015
Mohcd-rad program. unit renovation (kitchen & bathroom) conversion of 6 ada unit & 2 audio/visual units. window replacement new enclosed entry lobby, electrical, mechanical, elevator upgrades.
-
Jan 2016
Rev. to 201503201474 -to provide 1 ada parking space.
-
Mar 2016
Upgrade existing fire alarm system due to interior improvement in the building. voluntary install new smoke detector on 2/f office area, install 3 new power supply panels on 3/f, install notification appliances & smoke detector in new ada rooms. t.i. permit application 201503201474.
-
Mar 2016
To comply with nov 201604671: install 30 evac signs.
-
Jun 2016
Revision to ref pa 2015 0320 1474: new window replacement detail and elevation attached.
-
Jan 2017
Landscape and irrigation including renovation or replacement of irrigation system, site pavement, site furnishing and planting.
-
Jan 2017
Revision to permit application 201503201474 - new electrical room for switch gear replacement.
-
Feb 2017
Revision to permit application 201503201474, revise full scope of work in #501 to remain, revise total unit count from 110 to 109 due to #224 has been converted from a dwelling to an office for management at the building.
-
May 2017
Permit revision to pa 2017-0130-8219 - revised main courtyard.
-
Jun 2017
To obtain a final inspection for work approved under permit application 201603091574. all work is complete.
-
Aug 2017
As-builts drawings f/a permits under permit application 201603091574 & 201706300860.
-
Aug 2017
Revision to 201701318273. reduce scope of work. eliminate previously proposed wall and door in mechanical/boiler rm.
-
Oct 2018
Emergency responder radio coverage system.
-
May 2019
Design build to an existing (e3) fire alarm. the existing horns in all dwelling units will be removed and replaced with new lf sounder. fdu will pull new wire from existing box location to new sounder location. fdu will provide monitoring and annunicator to interface with new errcs.
-
Sep 2019
As built sprinkers for pa201905080062.
-
Jul 2020
To replace bda with combo and program sq ft frequencies. to upgrade donor antenna and point towards twin peaks. all other errc's will remain unchanged.