4092–4096 18th Street
Castro (Eureka Valley) · San Francisco, CA 94114
Permit history
-
Jul 1992
Tenant improvement of existing restaurant.
-
Aug 1995
Reroofing.
-
Jul 1998
Complete ti of space, new electrical & mechanical as well.
-
Aug 1999
Interior remodel to coffee cafe.
-
May 2003
Installation of bagel machine and rearrange counters for coffee and oven.
-
Jun 2004
Relocated existing counters equipment and furniture add 3 compartment sink and hand sink to comply.
-
Feb 2008
On 1st floor & roof top: provide 2 new split systems units - mechanical system with the condensing vent on rooftop & the fan coil on 1st floor providing cooling, units weight are les than 400 lbs.
-
Jul 2008
Existing vacant tenant space to be remodeled into a juice bar limited to 15 seats existing mechanical & existing lighting to remain-modify ceiling above service area.
-
Sep 2008
Demolition existing retail fixtures, existing finishes existing selected non struc partitions to accomadate new retail &inform'l area for historical society abd sq ft tourism inform'n area. demolition existing nonstruc alum. store frt sys to accom 2 new public access atm bank mach. mep under sep permit.
-
Jan 2010
New moment and footing @ front of building. all work interior on vacant space.
-
Nov 2010
Converting retail to specialty food, self-service. remodel/upgrade ada bathroom, new service counter, non-bearing partition, misc electrical & plumbing.
-
Jun 2012
Add class 1 hood & cooking equipment to former soup/salad restaurant. new tenant-add small partition walls (2), demolition front counter area. new opening in interior kitchen wall. replace front tiles (a lot missing).
-
Jul 2012
Ti to existing cafe of existing starbucks. update walls, floors, furniture, casework, bar equipment, new lighting, mechanical diffusers. new storefront location and finishes.
-
Aug 2012
Interior non structural demolition of e coffee shop. all work to comply with sfbc ab017. no exterior work.
-
Aug 2012
Revision to app#201207034029. alteration to mep layout and system. provide fire seperation for tenant spaces. new colums - structural under seperate permit.
-
Sep 2012
Install ul300 fire system into kitchen hood.
-
Nov 2012
Revision to app#201207034029. install new 6"x36" door activator at entry door.
-
Sep 2013
Soft story retrofit per sfbc chapter 34b fema p-807. seismic upgrade to comply with soft story ordinance, new mement frame. ** maher: compliance with ordinance no# 155-13 not required **.
-
Dec 2014
Commercial tenant improvement, new yogurt shop in place of former juice shop; maher n/a.
-
Jul 2017
To comply with complaint # 201788671, r&r fire damaged, framing, siding, trim window tram & sash on hte exterior & replace fire damaged flooring, electrical wiring, walls & ceilings, in 2 two units.
-
May 2018
Reroofing no propane torch on roof.
-
Oct 2018
Reconfigiure floor plan, new hood i (4'x12') new quarry tile fl. with quarry tile cove (work area) new ansual fire suppression system under seperate permite.
-
Apr 2019
Ansul system update. ref 201810244060.
-
Sep 2021
Reconfigure floor plan. new ada accessible counter for pick up only.
DBI holds 55 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 55. 7 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update