900 Kearny Street
Chinatown · San Francisco, CA 94133
Permit history
-
Dec 1981
Sign - erect.
-
Dec 1982
New construction.
-
Sep 1988
Tenant improvement as per plans.
-
Apr 1991
Tenant improvement.
-
Oct 1996
Cti-1 floor 7th el me sp.
-
Apr 1997
Cti 1 3rd fl el me sp.
-
Jun 1997
Cti-2 el, sp, me, ls. 3rd floor.
-
Dec 2000
Oti-1 5th floor ltg, me, ls, spr.
-
Jan 2001
Oti-2, el, me, sp 5th floor.
-
Nov 2011
3rd floor-minr t.i.-construct 1 conference room, 2 offices, partition, related electrical & hvac. install missing ceiling tiles & lights. demolition permit application 2010-1214-6636.
-
Jun 2018
5th floor: architectural only (ele, plumbing, sprinklers by others) create space for offices.
-
Sep 2018
Reroofing.
-
Jun 2019
Ste 700: office tenant improvement to include construction of offices, mechanical, electrical, plumbimg, & fire sprinkler.
-
Jan 2021
#200: this project involves modification of & expansion of existing t.i. to include selective demolition & construction of non-load bearing partitions. new ceiling grid & tile, nw light fixtures, new office doors & frames, salvage & reuse of existing selected materials if practicable, millwork & nw finishes.
-
Jun 2021
Suite 388: modification of existing t.i., construction of non-load bearing partitions, existing ceiling, grid & tile, light fixture relocation & new including reswitching, new doors/frames, salvage/reuse of existing selected materals, new millwork, sink, new finishes.
-
Sep 2021
3/f suite 333: modification of existing t.i to include construction of non load bearing partitions, modification of existing ceiling, grid and tile, light fixtures and relocation and re-switching, new office doors and frames, salvage and reuse of existing selected materials ande new finishes.
-
Feb 2022
Ab17 demolition e gr level tenant suite, community stairs to the basement level, partial basement leel partitions, millwork, finishes.
-
Apr 2022
Ste 610 & 625: tenant improcement. includes construction of non-load bearing partitions. modification to existing ceiling grid, & tile. light fixture relocation. new switching, new office door & finishes, millwork, sinks & finishes.
-
May 2022
2nd fl ste 200: tenant improvement including new partitions, ceiling, lighting break room + mechanical, electrical, plumbing.
-
May 2022
Suite 610 & 625: installation fo new electrical fixtures, plumbing fixtures and mechanical ducting. new receptacles and lighting controllers. new breakroom plumbing. ref ti permit 202204212713.
-
Jun 2022
5th floor: demolition and construction of non load bearing partitions for a new break area and server room; installation of new lighting fixtures and switching and new storage door rooms; door and frames salvage and reuse.
-
Jan 2023
Change of use from bank to design professional and 4 tenant spaces. tenant improvement of basement, ground to include selective demolition, construction of new non-load bearing partitions, new ceiling grid & tile, new light fixtures, new office doors and frames. mep deferred. fire sprinkler & fire alarm.
-
May 2023
2/f only: t.i. to include selective demolition & constructon on non-load bearing partitions, new ceiling grid, tile, new light fixtures including re-switching new office doors & frames, salvage & reuse of existing selected materials if practical & new finishes, accessible restroom are existing to remain.
-
Jul 2023
2nd fl - mechanical for pa 2023-0518-8064.
-
Jan 2024
Install 1 vrf condensing unit & 6 fan coils- air distribution, ductrowrk & piping for basement & 1st floor layout, mep for permit application 202312182690.
DBI holds 115 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 115. 7 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the developer and the early tenants. Submit an update