42 Stockton Street
Department store
-
1909
Built.
-
February 4, 1909
Morenson construction company contracted for structural steel and cast iron, galvanized iron and tin work, sewering and standpipes on a five-storey and basement brick building, at $10,012.
-
Dec 1982
Miscellaneous.
-
Feb 1993
Cti 1 6th el me sp.
-
Apr 1993
Hvac mechanical tenant improv/air distribut exist system/install.
-
Jul 2001
Street space.
-
Jan 2006
Interior demolition on all floors. removal of existing escalators. new slab openings on all floors for new stairs. (2) no exterior work under this permit.
-
Apr 2006
Tenant improvement for barneys new york on all floors. new m.e.p., partitions and interior finishes fire alarm and sprinklers under seperate permit. no exterior work.ref. appl#200601192583.
-
Jun 2006
Renovate existing facade of building. exterior work only. sprinkler work under separate permit.
-
Jul 2006
1st floor tenant improvement of retail space. all exterior work under seperate permit. interior work only.
-
Aug 2006
New fire alarm system for low-rise retail building.
-
Jan 2007
Fire sprinkler system build back 5th, 6th, and 7th floors 353 sprnkr.
-
Jan 2007
Fire sprinkler system. 239 new speakers, 3rd & 4th floors.
-
Jan 2007
Basement level-fire sprinkler system-190 speakers at basement.
-
Apr 2010
Construction of a closure wall to enable abandonement of approx 1400 sq ft of existing building area located in the basement beneath the sidewalk and outside the property line. no change in use. tenant improvements under seperate permit.
-
Apr 2010
Basement renovation to abandon sub-sidewalk space (1428 sq ft.) for new subway station. sprinkler and fire alarm uner seprarate permit. closure wall under separate permit.
-
Apr 2015
Basement - ti @ portion of basement only. work woll nclude a communicating opening b/w new retail area @ 2 stockton & existing retail are @ 48 stockton (77 o'farrelll).
-
Jun 2015
Ti portion of 3rd fl only. will include partital non structural demolition and minor renovation to retail and stock areas where indicated.
-
Dec 2015
5th floor: t.i. to convert retail department. work includes non-structural demolition and construction of new partitions millwork and finishes.
-
Dec 2015
2nd floor: t.i. to convert retail department. work includes non-structural demolition and construction of new partitions millwork and finishes.
-
Dec 2015
Exterior storefront renovations including removing a portion of storefront & constructing a storefront in opening. removing a canopy & patching the storefront where it is removed. adding awings.
-
Jan 2016
1st floor: ti- to expand ground floor retail space into adjacent suite; with in the bld/ work includes demolition of non load bearing partitions, doors, millwork, furnishing & finishes; and construction of new partitions and millwork and finishes.
-
Mar 2016
5th floor: stock shelving for retail use.
-
Jul 2016
Change of use on 6th floor from retail to restaurant, work includes construction of new partitions and bathrooms. no change in gross sq. footage.
-
Nov 2016
Deferred mep work. ref #201607182600. scope includes new roof top mechanical equipment.
-
Apr 2018
3, 4, 5 & 6th floors - fire alarm work for the "barney's" remodel add smoke curtains on floors 3, 4 and 5; additions are 18 smoke detectors, 2 heat detectors, 16 duct detectors, 3 modules, 22 horn/strobes, and 9 strobes. ref pa 2017-1010-0834.
DBI holds 75 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 75. 1 of them are nominal $1 street-space or sidewalk permits. 1 expired permit is not shown.
Nearby
- 17–25 Stockton Street Same street
- 46–48 Stockton Street Same street
- 2–30 Stockton Street Same block
- 750–780 Market Street Same block
- 111 O'Farrell Street Around the corner
- 24–34 Ellis Street Around the corner
- 20–26 O'Farrell Street Around the corner