750–780 Market Street
Union Square · San Francisco, CA 94108
-
1908
Built.
-
1908
Phelan Building, designed by William F. Curlett.
-
1980s
Restoration of the Phelan Building by architect Piero Patri.
-
Dec 1981
Otc alterations permit.
-
Jun 1997
Alterations to shell & core, andicap accessibility upgrade.
-
Mar 2009
Tenant improvement of 6th. floor office space. new partitions, restrooms, restrooms and finishes. all mep, fire alarm and sprinkler under separate permit.
-
Aug 2010
Demolition and construction for full floor ti approx.(26, 000 sq ft) to include new walls and finishes all work on 2nd floor. no increase in office space.
-
Sep 2011
5th floor -tenant impr comm office consists of demolition of existing non structructural partitions & ceilings, construction of new non structural partitions, acoustical ceilings, lighting, elctical & finishes. mechanical, electrical, plmg life safety and sprinklers are to be disign build & under seperate permit.
-
Jan 2012
Electrical and mechanical for ti work on the 5th fl. add, relocate, and remove fixtures and equipment. refer to 201109134435.
-
Jun 2012
Ti minor interior demolition of nonstructural. new walls, fixturization of sales floor. new plumbing fixtures in existing restrooms. new fitting/dressing rooms and cashwraps with remodel of existing employee breakroom & office.
-
Oct 2012
3rd floor: tenant improvement on 3rd floor to demolition and construct new partitions, doors and finishes, mechanical/el/sp/ls on seperate permit.
-
Oct 2012
4th floor: tenant improvement on 4th floor to demolition and construct new partitions, doors and finishes, mechanical/el/sp/ls on seperate permit.
-
Nov 2012
3rd floor: mechanical, electrical, plumbing for 3rd floor t.i. to remove, relocate and install equipment and fixtures. please refer to app#201210041301 for t.i. work.
-
Nov 2012
4th floor: mechanical, electrical, plumbing for 4th floor t.i. to remove, relocate and install equipment and fixtures. please refer to app#201210041302 for t.i. work.
-
Feb 2013
9th floor tenant improvement to construct rated enclosure for emergency egress & elevator lobby as well as new partitions & ada upgrade restrooms & shower rooms, mep, sprinklers & fire alarm under separate permit. unoccupied floor.
-
Dec 2013
Tenant improvement on 10/f to include new construction of non-load bearing partitions, ceiling, floors and wall finishes. rated stair enclosures and new single & multi accommodation restrooms & showers.(compliance with maher ordinance no.155-13 not required).
-
Dec 2013
Mechanical & electrical work for tenant improvement on 9/f. t.i. permit application 201309247571.
-
May 2014
On 8th floor - new non-structural partitions ceiling & lighting... millwork finishes. non structural demolition. upgrade toilet rooms. no change in occupancy, use, or area. na for maher ordiance.
-
May 2014
Remove existing roof. install new single ply roof membrane. repoint on back side of parapet only (not ornamental facade) as part of reflashing and waterproofing.
-
Jun 2014
T-24 work for ti on 8th floor to install new equipment. please refer to permit application 2014-0516-5944 for ti work. maher n/a.
-
Sep 2014
7th floor: new construction of non-load bearing partitions, ceilings, floor & wall finishes, rated stair enclosures and new single & multiple accomodation restrooms; maher n/a.
-
May 2015
4th floor: ti- partial demolition, limited lipgrades. new shower room & conference room. maher na. structural, mep, life safety, sprinklers under separate permit.
-
Dec 2016
3rd floor: ti includes demolition of non structural partition & millwork; buil non structural partitiona; all new or revised meps/fire/life safety under sep permit blg fully sprinklered maher na.
-
Feb 2017
1/f- interior tenant improvement to include selective demolition, new partition walls, suspended ceilings, millwork, finishes and corresponding mechanical/plumbing/electrical.
-
Jan 2018
2nd floor - ti include the demolition of non structural celining elements and bld new non structural partitions and mill work. all new or revised meps, life safety and sprinkler work will be design build and submitted sep. str, stair and tech platform submitted sep. demolition 201712196895, ti floor sprinkler, bld.
-
Jan 2019
11th floor: interior t.i. 11, 100 sq ft. demolition of lighting, plumbing and finishes. new construction to include lighting, plmg, and finishes. modification to existing partition and doors. no structural work.
-
Dec 2022
Project includes the rehabilitation & voluntary structural upgrade of the historic penthouse residence on the roof of 760 market. work includes interior and exterior rehabilitions of walls, windows, doors, roof ornament skylights, kitchen, bath and all associated mep. per coa motion n o 0459.
-
Sep 2025
2/f: tenant improvement includes demolition of non-structural partitions, ceilings, light fixtures, doors, and finishes. construction of non-structural partitions, ceilings, light fixtures, doors, glazing, millwork, and finishes. accessibility upgrades at existing restrooms. mep defer.
DBI holds 364 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 364. 19 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 744 Market Street Same street
- 757 Market Street Same street
- 2–30 Stockton Street Same block
- 46–48 Stockton Street Same block
- 24–34 Ellis Street Around the corner
- 111 Ofarrell Street Around the corner
- 100–130 Stockton Street Around the corner