303–353 Second Street
Office building
-
1937
A permit for interior alterations was taken out here in 1937 for the U.S. Rubber Company; a one-storey warehouse and incinerator were applied for in 1955, and the building came down in 1973, leaving a paved and striped parking lot.
-
1938
The Schilling Company applied in 1938 to build two concrete silos here for coffee storage; its offices were remodelled under permits of 1953 and improved outside in 1955, and the office building was demolished in 1973.
-
1988
Built.
-
Feb 2000
Oti-1 el me ls sp 10th floor.
-
Jul 2007
Reconfiguration of office space for training center. demolition under separate permit. training conference and private offices and open office space, mep, under separate permit.
-
Apr 2008
6/f south tower-tenant improvement includes new drywall, ceiling work, light fixtures, new doors & finishes. mechanical & electrical work to include installation & relocation of vav boxes, ducting, heat pumps & fire smoke dampers, lighting, data and outlets. ls under a seperate permit.
-
May 2009
7th fl & basement - north level "d": t.i. demolition of non-structural partitions & build new non-structural partitions, new & revised mechanical, electric, plumb & life safety, generator and fuel system, sprinklers, life safety under separate permit.
-
Oct 2010
9th floor single tenant floor t.i. work will include new drywall, ceiling work, light fixtures, new doors & finishes (no-structural work). all existing fire rated construction to remain, existing sprinkler & life safety system to remain fully operational throuhout construction.
-
Feb 2011
Interior remodel of north and south lobbies. exterior plaza rennovation consisting on new aluminum and glass storefronts, exterior "fins" and "eyebrows". new plaza landscape and hardscape.
-
Aug 2013
8th floor-tenant improvement-construct all new partitions, doors, finishes for new tenant. no new work to core or restrooms. m.e.p, life safety, sprinklers to follow on seperate permits.
-
Feb 2015
Tenant improvements on 7th floor - conference rooms, private offices, pantry, open offices & phone rooms. mep under separate permit. maher - not req'd.
-
Mar 2015
Mechanical & ele work associated with approved permit application 2015 0223 9019 including (ne) lighting & hvac/ life safety under seperate permit maher- not req'd.
-
Feb 2017
5th level: ti - new partitions & finishes. mep deferred. maher na.
-
Mar 2018
6th floor: t.i. to include new partitions, doors, frames, hardware glazing millwork addition unisex ada restrooms, electrical, mechanical, and plmg deferred. n/a for maher.
-
May 2019
Ti to 7th fl to include new non0load bearing partitions, floor finishes, ceilings, millworks. mechanical, electrical, life safety and sprinkler under separate permit.
-
Jun 2019
8th floor, t.i. new non load-bearing partitions, floor finishes, ceilings, millwork.//operation permit for assembly space required from sffd// vif card readers in elevator lobby, two way communication required.
-
Feb 2020
Full floor tenant improvement on the 3rd fl to include new non rated partitions, breakrooms all gender restrooms, mothers room and upgrade multi occupant restrooms. new finishes. mep sep permit.
-
Jun 2020
Ti of existing office space on the entire 10th fl. work includes non-structural partitions, mep, finishes, and re-cladding of an existing communicating stair.
-
Jun 2020
Suite #350: ti work entails construction of new non-bearing partitions, millwork, ceiling system with new lighting, doors & frames, power & communication, fixtures & furniture systems, carpet & paint finishes. maher na.
-
Jul 2020
Ti of existing office space on the entire 9th fl. work includes non-structural partitions, new lighting, ceilings, doors, carpets and paint. mep included.
-
Jan 2021
6th floor: t.i. to include new non rated partitions, breakroom, all gender restrooms, parents room. upgrade existing mens and women's restrooms new finishes. mep, life safty and fire sprinkler under seperate perimit.
-
Jan 2021
7th fl tenant improvement to include new non-structural partitions, multi purpose room expansion, all gender restrooms, upgrades to mens & womens restrooms, interior finishes.
-
Mar 2022
4/f suite n401 & n450: demolition of non-structural partitions, ceiling, lighting, millwork and finishes. new construction of non-structural partitions, ceiling, lighting, millwork and finishes.mep will be deferred submittal.
-
Jan 2023
Reroofing.
-
Jun 2023
5/f: interior t.i. new non-load bearing partitions, glazing, doors, millwork, & finishes. mep.
DBI holds 1,037 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 1,037. 18 of them are nominal $1 street-space or sidewalk permits. 2 expired permits are not shown. The 2025 assessor's roll dates this parcel 1988, which is the office building that replaced the buildings described.
Nearby
- 299 Second Street Same street
- 350 Second Street Same street
- 66–76 Lansing Street Same block
- 43–45 Lansing Street Same block
- 515 Folsom Street Same block
- 386–390 1st Street Same block
- 601–611 Folsom Street Around the corner
- 568 Folsom Street Around the corner