529–531 Commercial Street
Financial District · San Francisco, CA 94111
Permit history
-
Aug 1981
Additions alterations or repairs.
-
Dec 1981
Additions alterations or repairs.
-
Mar 1982
Additions alterations or repairs.
-
Dec 1989
E.w.o. (s).
-
May 1995
Umb seismic upgrade special procedure.
-
Jun 1998
Earthquake retrofit/structural remodeling/anchorage at floor.
-
Jul 1999
New fire protection system.
-
May 2000
To receive permits kitchen shafts & canopy as built-rev. to permit application 200002101558.
-
May 2000
Install 2 new type 1 hood system, and 2 make-up air system.
-
Jun 2000
Install pyrochem fire suppression system in kitchen hood.
-
Sep 2000
Install facp to onitor water flow/smoke detectors.
-
Feb 2001
Interior partition renovation, add accessible bathroom, update finishes & fixtures.
-
Apr 2004
Demolition interior walls, ceilings, soft interior demolition on 3rd & 4th offices.
-
Jun 2004
Refinish existing sub floor, diamond coate textured walls, replace 14 existing windows with similar type same siz.
-
Nov 2004
Install new fire suppression system in kichen hood.
-
Feb 2012
New concrete floor will be placed above existing concreete floor in kitchen area. seal new concrete floor and paint with epoxy paint @ restaurant area only.
-
Mar 2013
Roof repairs at west sife and roof maintenance at flat roof - clean. apply apoc #211 surface.
-
Jul 2013
Remove existing casework equipment and finishes. construct new millwork. install new equipment.
-
Oct 2013
Install 6-ton rooftop heat pump with exposed ducts.
-
Jul 2018
New partition, new finishes for tenant improvement. all work on second floor.
-
Aug 2019
Mep submittal for 201807194945.
-
Nov 2021
1st/f: replace existing exterior door with new in-kind storefront with low energy door operator & new auto door operator. 3rd/f: upgrade existing baths to ada compliance. modify existing kitchenette & private office, provide workstations. 4th/f: modify existing private office and existing conference rm.
-
Jul 2022
Alteration to existing restaurant/bar including accessibility upgrades to existing restrooms, replacing existing equipment and reparing finishes in-kind.
-
Feb 2023
Finish and install (1) ansul r-102 fire suppression system in the main kitchen area, ground floor. ref permit application 202207158538.
DBI holds 40 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 40. 8 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update