160–180 Sansome Street
Financial District · San Francisco, CA 94104
-
1965
Built.
-
1966
The Hongkong Bank Building opened to tenants, with about 92,500 gross square feet of office space.
-
Nov 1981
Additions alterations or repairs.
-
Jan 1996
Cti-1 17/f el me sp.
-
Nov 2003
New const. in shell space previously occupied by a bank includes partitions doors frames casework.
-
May 2008
14th floor-ti including rated elevator lobby with rated won door, non-bearing partitions, millwork and ada accessible restrooms. sprinklers and fire alarm separate permit. sprinkler system is completed throughout building- umbrella permit to be signed off before occupancy can be granted.
-
May 2008
Change of use occupancy on 3rd floor existing office to 2 residential apartment units. interior works only, each unit includes 2 bedrooms and 2 bathrooms.
-
Sep 2008
Tenant improvement of 10th floor to incude rated elevator lobby with automatic fire rated door, non bearing partitions millwork and ada accessable restrooms. mep and life safety to be filed separately.
-
Jun 2010
Ti 4th fl - incl rated elevator lobby with fire rated won door, non bearing partitions & millwork. ada accessible restrooms.
-
Jul 2010
Storefront replacement & expansion of lobby (t.i.work).
-
Sep 2012
Tenant improvement of 3rd, 7th and 8th floors to include rated elevator lobby with rated door, non bearing partitions and millwork and ada accessible restrooms.
-
Jun 2013
6th & 9th floors-tenant improvement-removal & construction of non structural partitions, new finishes throughout. m.e.p, fire life safety & sprinkler under seperate permits.
-
Nov 2013
4th & 15th floor - demolition int partition & finishes, new walls, doors & finishes, rewire space to new layout, relocate power outlets, modification of existing hvac system. modification of existing toilets. f/a sprinkler under separate.
-
Oct 2014
2nd floor demolition of existing concrete topping slab and existing waterproofing membrane. installation of new hot rubber waterproofing membrane. pour new concrete topping slab work at 2nd floor courtyard; maher n/a.
-
Jul 2015
8th floor t.i. include new construction of non structural partition walls, replacement of light fixtures, add a break area with sink. maher n/a. mep included - sprinkler & fire alarm sep permit.
-
Oct 2016
3rd floor tenant improvement limited to non-structural interior walls & floor finishes. meps, life safety etc will be design build & submitted separately, n/a ordinance #155-13.
-
Mar 2018
Grnd floor & mezzanine - new fitness club. new fixtures, finishes, equipment, bathrooms, kitchenette, mep. no exterior work. fire protections under sep permit maher na.
-
Feb 2019
Interior non structural demolition of 2nd, 3rd, 4th, 6th, 7th, 9th, 11, 12, 14, 15, 16, 17, 18th floors in cluding partitoins, flooring, ceiling, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all mep, fire alarm, fire sprinkler, structural work shall be.
-
Mar 2019
Interior remodel of 9th and 11th floor only. non stuctural remodel to include partitions, floorings, ceilings, furnishings finishes etc. no change to other floors in building or existing egress path to street. all fire alarm, fire sprinkler and structural work under seperate permit.
-
Mar 2019
Interior remodel of 3rd & 4th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.
-
Mar 2019
Interior remodel of 12th & 14th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit. maher n/a.
-
Mar 2019
Interior remodel of 6th & 7th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep permit.
-
Mar 2019
Interior remodel of 15th & 16th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.
-
Mar 2019
Interior remodel of 17th & 18th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.
-
Mar 2019
Interior remodel of 2nd fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.
-
May 2019
Mep for 17th and 18th fl ti under 201903054399.
-
Oct 2023
Replacing fusible link smoke dampers with new automated fire smoke dampers.
DBI holds 212 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 212. 6 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 155 Sansome Street Same street
- 200–206 Sansome Street Same street
- 140–142 Sansome Street Same block
- 235 Pine Street Same block
- 100–130 Sansome Street Same block
- 201–221 Pine Street Same block
- 200–216 Pine Street Around the corner
- 301 Pine Street Around the corner