37.7919, −122.4006 A locator map appears here once a Mapbox token is configured.

160–180 Sansome Street

Financial District · San Francisco, CA 94104

  • Office building
  • 17 stories
  • Zoned C3O
  • District 3
  • Historic status: unevaluated
37.7919, −122.4006 Street View appears here once a Google Maps embed key is configured.
151,326 sq ftBuilding area
10,001 sq ftLot area
10Rooms · 20 baths
  1. 1965

    Built.

  2. 1966

    The Hongkong Bank Building opened to tenants, with about 92,500 gross square feet of office space.

    444 Market Street Project DEIR, SF Dept. of City Planning, 1975
  3. Nov 1981

    Additions alterations or repairs.

    Complete Permit 8109835 $$$ $4,500
  4. Jan 1996

    Cti-1 17/f el me sp.

    Complete Permit 9601106 $$$ $242,000
  5. Nov 2003

    New const. in shell space previously occupied by a bank includes partitions doors frames casework.

    Complete Permit 200311120004 $$$ $265,000
  6. May 2008

    14th floor-ti including rated elevator lobby with rated won door, non-bearing partitions, millwork and ada accessible restrooms. sprinklers and fire alarm separate permit. sprinkler system is completed throughout building- umbrella permit to be signed off before occupancy can be granted.

    Complete Permit 200805152128 $$$ $500,000
  7. May 2008

    Change of use occupancy on 3rd floor existing office to 2 residential apartment units. interior works only, each unit includes 2 bedrooms and 2 bathrooms.

    Cancelled Permit 200805162287 $$$ $300,000
  8. Sep 2008

    Tenant improvement of 10th floor to incude rated elevator lobby with automatic fire rated door, non bearing partitions millwork and ada accessable restrooms. mep and life safety to be filed separately.

    Complete Permit 200809232444 $$$ $472,043
  9. Jun 2010

    Ti 4th fl - incl rated elevator lobby with fire rated won door, non bearing partitions & millwork. ada accessible restrooms.

    Complete Permit 201006114296 $$$ $250,000
  10. Jul 2010

    Storefront replacement & expansion of lobby (t.i.work).

    Complete Permit 201007217078 $$$ $250,000
  11. Sep 2012

    Tenant improvement of 3rd, 7th and 8th floors to include rated elevator lobby with rated door, non bearing partitions and millwork and ada accessible restrooms.

    Complete Permit 201209280845 $$$ $375,000
  12. Jun 2013

    6th & 9th floors-tenant improvement-removal & construction of non structural partitions, new finishes throughout. m.e.p, fire life safety & sprinkler under seperate permits.

    Complete Permit 201306129281 $$$ $281,000
  13. Nov 2013

    4th & 15th floor - demolition int partition & finishes, new walls, doors & finishes, rewire space to new layout, relocate power outlets, modification of existing hvac system. modification of existing toilets. f/a sprinkler under separate.

    Complete Permit 201311051201 $$$ $280,000
  14. Oct 2014

    2nd floor demolition of existing concrete topping slab and existing waterproofing membrane. installation of new hot rubber waterproofing membrane. pour new concrete topping slab work at 2nd floor courtyard; maher n/a.

    Complete Permit 201410068200 $$$ $395,000
  15. Jul 2015

    8th floor t.i. include new construction of non structural partition walls, replacement of light fixtures, add a break area with sink. maher n/a. mep included - sprinkler & fire alarm sep permit.

    Complete Permit 201507242444 $$$ $854,280
  16. Oct 2016

    3rd floor tenant improvement limited to non-structural interior walls & floor finishes. meps, life safety etc will be design build & submitted separately, n/a ordinance #155-13.

    Complete Permit 201610190683 $$$ $342,244
  17. Mar 2018

    Grnd floor & mezzanine - new fitness club. new fixtures, finishes, equipment, bathrooms, kitchenette, mep. no exterior work. fire protections under sep permit maher na.

    Complete Permit 201803153746 $$$ $900,000
  18. Feb 2019

    Interior non structural demolition of 2nd, 3rd, 4th, 6th, 7th, 9th, 11, 12, 14, 15, 16, 17, 18th floors in cluding partitoins, flooring, ceiling, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all mep, fire alarm, fire sprinkler, structural work shall be.

    Issued Permit 201902132888 $$$ $225,000
  19. Mar 2019

    Interior remodel of 9th and 11th floor only. non stuctural remodel to include partitions, floorings, ceilings, furnishings finishes etc. no change to other floors in building or existing egress path to street. all fire alarm, fire sprinkler and structural work under seperate permit.

    Issued Permit 201903054407 $$$ $300,000
  20. Mar 2019

    Interior remodel of 3rd & 4th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.

    Issued Permit 201903054428 $$$ $300,000
  21. Mar 2019

    Interior remodel of 12th & 14th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit. maher n/a.

    Issued Permit 201903054423 $$$ $300,000
  22. Mar 2019

    Interior remodel of 6th & 7th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep permit.

    Issued Permit 201903054410 $$$ $295,000
  23. Mar 2019

    Interior remodel of 15th & 16th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.

    Issued Permit 201903054417 $$$ $300,000
  24. Mar 2019

    Interior remodel of 17th & 18th fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.

    Issued Permit 201903054399 $$$ $300,000
  25. Mar 2019

    Interior remodel of 2nd fl only. non-structural remodel to include partitions, flooring, ceilings, furnishing, finishes, etc. no change to other floors in building or existing egress path to street. all fire alarm/sprinklers & structural under sep pemrit.

    Issued Permit 201903054435 $$$ $150,000
  26. May 2019

    Mep for 17th and 18th fl ti under 201903054399.

    Issued Permit 201905130467 $$$ $400,000
  27. Oct 2023

    Replacing fusible link smoke dampers with new automated fire smoke dampers.

    Complete Permit 202310178851 $$$ $369,000

DBI holds 212 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 212. 6 of them are nominal $1 street-space or sidewalk permits.