762 Fulton Street
Hayes Valley · San Francisco, CA 94102
-
May 1982
Building use: cultural ctr.
-
Mar 1984
General renovation mechanical and electrical work.
-
Sep 1984
Installation of sprinkler system on the 2nd & 3rd fl.
-
1989
A building put up for the Acme Brewing Company, used as the San Francisco Redevelopment Agency's Western Addition field office through the redevelopment years and turned over to the community in the late 1980s. The African American Art and Culture Complex moved in in 1989 — one of the city's six cultural centres, with galleries, a 206-seat theatre, dance studios and a conference room — and the San Francisco African American Historical and Cultural Society is housed here. Murals were painted at the centre in 1984 and 1996. Identified in 2024 as eligible for local landmark, California Register or National Register designation.
-
Oct 1990
Repair concrete shear walls, repair electrical. plaster #9022476.
-
Feb 1991
Epoxy grout cracks in concrete shear walls, electrical. repair.
-
Nov 1994
Restripe existing parking lot, install motorized gate fence.
-
Mar 1998
Reroofing.
-
Aug 1998
Modification to restrooms for people with disabilities.
-
Jul 2008
Ground floor, 2nd & 3rd floor - barrier removal project under cb 1134b.2, exception 2j. upgrade toilets on g/f, 2nd fl & 3rd fl, upgrade accessible parking, upgrade lobby lighting & ratip, upgrade some finishes.
-
Mar 2009
Relocate 8 sprinkler heads on 1st & 3rd floors.
-
Dec 2010
Replace existing building furnaces with newer, smaller and more efficient furnaces. the project's purpose is an energy efficent project.
-
Jan 2011
Replacement of 4 existing furnaces with new gas fired units energy efficient. using ex equip rooms and locations.
-
Mar 2013
Ada barrier removal work. provide new accessible boys and girls toilets on 2nd fl. provide 1 janitor sink in janitor closet. provide sink and counter area on 3rd floor breakroom. replace egress door at exit stair.
-
Dec 2014
Emergency facu replacement per csfm code interpretation 12-001 and information bulletin dated 9/4/2008.
-
Mar 2015
As built submittal for facu replacement. ref 2014-1203-2939.
-
May 2015
Upgrade electric panels down stream of main service. replace 30 kva transformer.
-
Feb 2018
No construction. establish occupancy for assembly permit.
-
May 2018
No construction. verifying occupant load calculations per 3 assembly rooms. revision to pa 2018-0226-2272 establish occupancy for assembly permit only to include a-2.
-
Nov 2018
Replace existing duct heater with new heaters on roof. 5 new dsd's.
-
Dec 2019
Revision to permit application 201805017873. to clarify occupancy use details per plan. no construction - no chnage to occupant load. establish occupancy for assembly permit only.
-
Jun 2021
Relocation of (4) sprinkler heads on the second floor. plug (1) head.
-
Aug 2021
Fabricate 6 evacuation maps with installation, 1x 1/f, 2x 2/f, 2x 3/f, 1x 4/f.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update