100–150 15th Street
Mission Bay · San Francisco, CA 94103
-
1944
Built as the Circus Foods salted nut mfg and food processing plant.
-
Sep 1995
Reroofing.
-
Apr 1999
Provide new common entry, toilet facilities, upgrade tenant.
-
Aug 2000
Installing new fire alarm system. @ground fl & mmezzanine to supervise flow and tamper switch.
-
Sep 2000
Provide t/i new elevator handicap accessible showers.
-
Mar 2001
Renew appln #200006051815 200008117656 to complete work.
-
Oct 2001
Add power exponder and light to esisting system.
-
Oct 2002
Build new 1 hr rate partition in office area and at steel columns.
-
Oct 2002
Provide support for carpet.
-
Oct 2002
Erect 10 ft high partitions in tenant space for furniture wholesale showrm electrical wrk under separate.
-
Nov 2002
Install new drywall partitions, carpet & tile flooring, install new light fixtures.
-
Feb 2003
Build new mezzanine to prev app 200210280058.remodel work all interior.
-
Mar 2003
New glass wall on 1st floor new wall on mezzanin level.
-
Aug 2003
Install non structural partitions 1st & mezz show rooms sprinklers under sep appln when required per.
-
Apr 2004
Permit application 9516126-200308011004-200302268376-new mezz level structural only.
-
May 2004
On groundfloor: create new storage room, paint, new under stairs walls - one hour assembly.
-
Nov 2004
Expand interior floor space at existing 2nd floor & add bath rooms to existing building per plan. all t.i. work under sep permit.
-
Nov 2004
Interior renovation of street level space upgrade lighting, demolition of tile ceiling & lights partital*.
-
Sep 2005
All electrical wiring and title 24 (building 32004/11/10/8944).
-
Apr 2006
Install garage exhaust fan, inline exhaust fan, boiler, co sensor fan, heat pump.
-
Oct 2006
Install new fire alarm system. 44 addressible devices, 8 strobes, 21 horn/strobe (ceiling), 28 horn strobe (wall), 1 bell, 36 so's/3 hds. fire alarm certification required.
-
Dec 2006
Revision 200411108944, relocate existing opening connnection per plan.
-
Mar 2016
Tenant improvement at existing retail building. installation of non-bearing interior wall & finish including m.e.p. fire sprinkler system under separate permit. n/a/ maher ordinance.
-
Aug 2016
Steel storage racks. fabricated metal. assembly on site maher na.
-
May 2021
Tenant improvement for an existing showroom space to new tile showroom space. new lighting, existing electrical panel to remain, existing hvac to remain. no change of use or envelope. sprinklers per nfpa 13 under sep permit.
DBI holds 70 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 70. 9 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update