1554–1560 Van Ness Avenue
Nob Hill · San Francisco, CA 94109
-
1917
Recorded in the city's survey of the Van Ness Avenue automobile corridor as a Hupmobile and Pontiac showroom; altered.
-
Jul 1992
Title 24 update-handicap toilets, new front doors, elev etc.
-
Sep 1992
New fire alarm system.
-
May 1995
Replace 2 multizone units with 10 separate gas/electrical air condtioner.
-
Aug 1997
Interior renovation incl soft demolition, new partitn, fire protect.
-
Sep 1997
Construct coffee cafe, incl partitions, cabinets, eqp, #9715275.
-
Sep 1997
Int construct a neighborhood svc sandwich shop incl cabinetr.
-
Sep 1997
Revise to app #9715275 for interior t/i signage & fire/prot.
-
Nov 1999
Remove post office boxes to expand open office banking.
-
Apr 2003
Shoring & underpinning required due to adjacent new const bpn #200212042782s on 1635 california st.
-
Jul 2004
Maintenance project remove existing damaged glass skylight and replace with built up roof with roof acces.
-
Oct 2004
Reroofing.
-
Mar 2008
Renovation of existing starbucks - replace some finishes, some cabinets, some equipments, no exterior work, reconfigure barrister bar, condiment table.
-
Nov 2008
Remove damaged wall and replace with new 2 hour walls at stairwell #3.
-
Nov 2008
Hvac retrofit. replace (14) rooftop ac units and repalce (2) return fan on roof.
-
2010
Identified in the city's survey of the Van Ness Avenue automobile corridor but not formally evaluated on a state historic resource form.
-
Mar 2012
Exterior work only - replace existing atm surrounds, update lighting.
-
Jan 2013
Interior non structural t.i to existing coffee shop. work to include relocation of existing equipment, new casework, new finishes, new floor sinks, flooring, furniture & relocation of existing lighting.
-
Mar 2013
Barrier removal-300 sq ft-demolition existing atm's, restore existing exterior elevations. new interior atm vestiblue, interior signage graphic wall. new & relocated lighting & sign lighting. minor mechanical to be design build.
-
Dec 2013
2nd floor - maher ord not required. demolition of interior partitions. new interior partitions for new tenant. reconfigure existing restrooms for accessibility compliance.
-
Mar 2014
Add 1 smoke detector, 1 power supply & 22 notification device.. ref #2013.1230.5309 under review). compliance with ordinance #155-13 not required.
-
Oct 2018
2nd floor. interior ti to convert existing open office to 3 private offices.
-
Feb 2019
Interior non-structural t.i. to an existing sgtarbucks, work to include relocation of existing equipment, new casework, new finishes, new flooring, furnature and new lighting. n/a for maher.
-
May 2021
Upgrade of existing fire system panel & cellular communications.
-
Jan 2026
Install (2) illuminated single faced wall signs: "wells fargo" (33' x 3'10") 5" thick.
-
Jan 2026
Install (1) illuminated double faced projecting sign: "wells fargo" (67" x 47") 5" thick.
DBI holds 55 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 55. 6 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update