Permit history
-
Jul 1990
Add new concrete & masonary enclosure for generator room.
-
Apr 1996
Cti-1 1stfl, el, me, sp.
-
Jun 1996
Install security system.
-
Jun 1996
Fire sprinklers.
-
Jun 1996
Cti 2 1st fl el.
-
Jul 1997
For record drawing on automatic door operator & handrails.
-
Jan 1998
Renew permit application 9607054 for final.
-
Jan 1998
Renew permit application 9713805 for final.
-
Aug 2005
Replace single service shipping, receiving door with two smaller service doors in same opening.
-
Apr 2008
Tenant improvements demolition/relocate existing partitions as indicated on plans. existing lighting, sprinklers, life safety/hvac to remain.
-
Jan 2009
Install 1 new 1.5 ton ductless spit system to serve existing guard room. mount rooftop condensing unit & wall hung fan coil. run refrigerant piping from cond. unit to fan coil. run condensate piping to nearest sanitary drain.
-
May 2017
Add two each fire sprinklers in existing electrical room maher na.
-
Nov 2017
Installation of 1.5 ton split system dx unit in server room. condensing unit install on roof. remove existing unit in server room.
-
Sep 2020
Barrier removal only -ada toilet upgrade of existing toilet rooms, partial demolition of men's toilet room, janitor's room & women's toilet room. new design/build hvac, electrical & plumbing s required. mep: design/build (in area of work only.
-
Nov 2020
Jc 5003 - modify sprinkler head locations to accomodate new ceiling & partition layout for existing restroom on 1st floor. total sprinklers this project = 6.
-
Nov 2020
Remove and replace 2 split systems.