Permit history
-
Jan 2000
Sign.
-
Aug 2004
Erect a new office, parking, assembly, fuel storage building.
-
Feb 2005
Excavation, shoring & underpinning for 55 9th st. (site permit permit application 200408111247).
-
Apr 2005
Remove 15"-20" of concrete from entire lot of an existingslab on grade parking lot for site preparation.
-
May 2005
Erect tower crane for construction of new building.
-
Aug 2011
To erect 17 stories, 273 units residential, retail & parking building.
-
Apr 2012
Excavation shoring, soldier beam with tieback and wood lagging; cantilever soldier beam and wood lagging. no shoring or underpinning work on adjacent properties. construction under separate submittal.
-
Aug 2012
Erect temporary crane for construction. ref 20110823049 new building.
-
Sep 2012
Installation of fire fighter breathing air system in entire building.
-
Jan 2013
Revision to issued addendum 1 - for foundation improvement, reference approved & issue permit application 2011-08-23-3049 s-1.
-
Feb 2013
Artwork installation along 55 9th st. reference approved & issued permit application 201108233049-s.
-
Sep 2013
Evacuation signs (59) for b1, b2, 1 - 17 floor & roof.
-
Nov 2013
Erect an electric single faced indirect new sign (portion letters attached to letters have 3 sides.
-
Nov 2013
To erect two electrical sign "ava sign".
-
Nov 2013
Interior non-structural, tenant improvement. leasing office for building. reference issued & approved permit application 2011-08-23-3049.
-
Sep 2014
To build out a newly constructed retail space to create a restruarant with kitchen, bathroom, bar area and coffee bar.
-
May 2015
Add 10 sprinklers & relocate 31 sprinklers on ground floor only. ref. appl. #2014.0917.6545. maher n/a.
-
Aug 2015
Installation of ul300 fire system. ref app#201409176545.
-
Sep 2015
1st floor: fire only permit, add 4 duct detectors, 2 monitoring modules, 10 speaker/strobes & 4 strobes to the existing system due to a tenant improvement.ref. building 201409176545; maher n/a.
-
Nov 2018
2 new roof top ladders mounted to penthouse wall.
-
Dec 2019
Ground floor demolition of fixtures and finishes of e restaurant. no ext changes, no structural work.
-
Dec 2020
Replace existing entry lobby door with new power-assist door. entry lobby door is for residential lobby only.
-
Feb 2021
Reduce height of existing metal sidewalk planters along 9th street. add new in-grade planting areas at specified areas adjacent to building. add new veritical extension to existing fense & street gate at north property line.
-
Jun 2021
To replace the errcs bda head end unit as well as the donor "roof" antenna to comply with sq ft frequencies. all other components remain unchanged.
DBI holds 38 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 38. 5 of them are nominal $1 street-space or sidewalk permits.
Caruso's Dream
The thirteen suspended pianos were unveiled on 23 February 2014, built from salvaged safety plate glass forty to sixty years old and Douglas fir milled out of the foundations of the demolished 1939 Transbay Terminal. At night they light in sequence with a recording of Enrico Caruso, who sang at the Grand Opera House the night before the 1906 earthquake and described it afterwards as his bed rocking like a ship at sea.