986 Mission Street
South Of Market · San Francisco, CA 94103
Permit history
-
Oct 1995
Erect sign.
-
Oct 2000
Barrier removal work includes a new stair restroom upgrade for all levels and replacement.
-
May 2015
Partial compliance with nov 201536851: remove unpermitted stove and walls at basement.
-
May 2015
Abate nov 201536851, 2nd fl. new bathrooms, partition wall. 5th fl: new bathrooms, partition walls.
-
May 2015
Replace existing commercial metal garage doors in like kind.
-
Jul 2016
5th fl new walls, doors, sidelights, power outlets and light fixtures. construct 2 new ada accessible restrooms.
-
Nov 2016
5/fl: change of occpancy on 5th floor from s-2 to b. includes modify existing 2 ada restrooms, install 4 phone rooms. work will include relocating doors and light fixtures and adding new walls, doors, power outlets and light fixtures. maher not req.
-
Jan 2017
3rd floor: construct new walls, doors, side lights, power outlets for new offices, storage and trash rooms and upgrade restrooms. replace all rusted drop ladder rivets, ladder runs, retaining washers and coffer pins. remove all obstructions on fire escape.
-
May 2017
1st fl/mezz: construction new ada bathroom & ada shower, new walls, doors, sidelights, power and associated lighting. no change of use.
-
Jun 2017
3rd fl: installation of more sprinkler heads for new layout. ref #201607182610.
-
Jun 2017
5th fl: move sprinkler heads for new layout. ref #201611142655.
-
Jul 2017
To replace the existing metal gate with new storefront at the main entrance (2 gates and 2 storefronts).
-
Jul 2017
1st floor: change the floor occupancy from s-2 to b. no new work other than reducing and changing locations of existing power outlets.
-
Aug 2017
Fire sprinkler: install 28 pendent quick response head and 1 sidewall head in mezzanine area on 1st fl.
-
Nov 2017
Modify existing automatic fire sprinkler system per tenant improvement, 28 new pendent sprinklers installed and 1 sidewall sprinkler to be added to existing system ref 201705257613.
-
Mar 2018
Change the floor occupancy s-2 to b on 3rd floor. no work under this permit other than reducing & changing locations of existing power outlets.
-
Apr 2018
4th floor - construct new walls, doors, sidelights, power outlets, and lighting fixtures, new ada bathrooms and showers.
-
Jul 2018
4th floor: change of use from storage to office. minor mep work. ref to permit application 2018-0403-5396.
-
Aug 2018
4th floor: installation of sprinkler heads for new office layout 13. ref app# 201804035396.
-
Oct 2018
Upgrade existing fire alarm system to include sprinkler monitoring and install new notification devices. ref permit application 201705257613, re sprinkler permit application 201711022946.
-
Dec 2018
Remove all elevator lobby smokes except one near facu, add ra next to facu, remove all relay modules. ref fire permit application 201810163311.
-
Aug 2022
Scaffold building facades. sound concrete. remove and replace unsound concrete in kind. this work does not fully comply with the requirements of ab-110 work being done to stabalize bad concrete in architectural details.
-
Jul 2023
G/f: interior tenant improvement including new non-load bearing walls, sofit & finishes, replacing light fixtures & modifying switching, adding electrical outlets, add exhaust fan at trash room, panic hardware at existing exit doors.
-
Jun 2024
Relocate existing upright sprinkler heads to pendant position for tenant improvement (32) heads.
DBI holds 36 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 36. 8 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update