1966
The Bellevue Hotel, where the National Planning Conference of Homophile Organizations met from 25 to 28 August 1966.
-
Jul 1985
Construction of partition walls & door assemblies.
-
Mar 1989
Interior soft demolition only.
-
Mar 1990
Architectural, structural, electrical/mechanical & sprinkler work.
-
Aug 1990
Repair footings.
-
Dec 1990
Design and install shoring system consist of underpinning.
-
May 1991
Work on street level floor & handicap bathroom on the lobby.
-
May 1991
Handicap exs. rump. bathroom on street level hotel lobby.
-
Jun 1991
Fire protection-sprinklers.
-
Oct 1993
Completion of arch. struc. electrical/mechanical and spk work-9005762.
-
Nov 1994
For bar, private dining and restaurant.
-
Jan 1995
Furnish & install new life safety fire alarm system for building.
-
Feb 1995
Construct gunite spa.
-
May 2000
Mount 1 18' omni antenna to the corner of existing building place associated equipment on roof below par.
-
May 2000
Street space use.
-
Sep 2000
Install one 18" omni whip antenna & associated equip shelter.
-
Jun 2011
Remove all sprint nextel wireless equipment, site will be repair back to original condition.
-
May 2014
Renovation of 6449 sq ft on lev 1 of a restaurant and meeting rom and 3147 sq ft of floor area added to level 2 for storage, meeting rooms, and offices. includes new floor area, walls, ceilings, stairs, casework and finishes, . non strucural demolition, fire sparinker and alarm and mep for level 2 are sep permit.
-
May 2014
Conversion of storage, meeting rooms, and offices on level 2 to 7 guestrooms. new exterior window openings at exterior work includes walls, ceiling, caseword and finishes. -maher- compliance with ordinance no. 155-13 not required.
-
Jul 2014
Demolition of non structural walls, plmg fixtures. work also includes minor electrical demolition. no exterior work included in this permit. work occurs on level one and level two. t.i. work under seperate permit ab-017. n/a for the maher ordinance #155-13.
-
Nov 2014
Installation of sprinkler ti in first floor restaurant and second floor new hotel units. construction 201405145770 and bracing included- 2 calc areas. heads deleted and new heads in place.; maher n/a.
-
Aug 2015
Remove old chiller and install new chiller. basement area, mechanical room. refrigerant monitoring under separate permit. maher na.
-
Aug 2017
1/f: voluntary replacment of the fire alarm panels (2) and the lobby aunnuciator for the monaco hotel. all new equpiment installed on floor 1. n/a maher.
-
Mar 2018
Reroofing.
-
Apr 2021
Levels 2-7: renovation of 27 guestroom bathrooms including new walls, ceilings, finishes, and plumbing fixtures. mep, fire sprinkler and alarm as necessary will be under a separate permit. no exterior work.
DBI holds 66 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 66. 10 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update