Cliff Hotel
491–499 Geary Street · Tenderloin
-
January 27, 1912
The Clift Hotel was announced for this corner: a fireproof hotel in the Italian Renaissance style on an 87 by 112 ft lot, estimated at $300,000, designed by MacDonald & Applegarth.
-
1913
Built.
-
1913
Cliff Hotel, designed by George Adrian Applegarth.
-
1984
Known as the Clift Hotel; it was among the rated buildings of the city's Downtown Plan inventory.
-
May 2000
Replacing partition in 48 double rooms to return to single rooms ar originally built.
-
Jul 2000
Remodel of 1st floor & lobby mezzanine, minor structural.
-
Jul 2016
Replace existing fans with new, note: weight of new "fan coil "not to exceed weight of existing "fan coil" maher na.
-
Oct 2018
Facade restoration & roof replacement. ** maher: n/a **.
-
Oct 2018
13th fl - model guestrooms on level 13, model two rooms.
-
Nov 2018
Renovations to the existing clift hotel. to include enclosure of the roof level & spanish suite terrace per city legislation file no 161068 determine occupant load for assembly space.
-
Apr 2019
Floors 2-17; renovation of existing guestroom & floor corridors.**maher n/a**.
-
Apr 2019
Renovations to existing clift hotel to incl new finishes & opening lobby walls to mezzanine & new lobby restrooms.
-
Sep 2019
Fire sprinkler ti - 109 pendents heads replaced, 6 pendents relocated, 6 pemdents added 14 deleted pendents, 27 sidewalls replace, 26 sidewalls relocate, 8 sidewall added 181 head total ref 201904248784.
-
Oct 2019
Tenant improvement for gr fl cafe in existing hotel with occupant load.
-
Oct 2019
Fire sprinkler ti: replace 176 pendent & 76 sidewall, relocate 9 pendent and 51 side wall, add 3 pendent and 25 sidewall, 30 pendent deleted, 341 head total. ref permit #201904248784.
-
Oct 2019
Fire sprinkler ti - replace 230 pendent and 84 sidewall heads. relocate 14 pendent and 74 sidewall heads, add 5 pendent and 36 sidewall heads, 45 pendent heads deleted total 443 heads ref pa 2019-0424-8784.
-
Nov 2019
Replacement of existing field devices with new devices to 1st & mezz fl only. minor floor plan changes to meet current code. no changes to existing services of ops.
-
May 2021
Renovations to the existing clift hotel (type 1, article 11 building) to include a new main entry marquee. 1. add an open building marquee over the existing sidewalk along geary street.
-
Nov 2023
Replace 2 existing rooftop cooling towers with new cooling towers & basin sweep filter, replace 1 existing basement condeser water pump serving ch-1 chiller with new condenser water pump, install new condenser water pump serving basement water source heat pumps.
-
Dec 2025
Exterior facade repair & stabilization, includes in kind replacement of brick (deteriorated), limted repoint, and discreet anchorage of localized masonry walls. all material to match existing and to follow secretary of interiors standards for rehabilitation.
DBI holds 98 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 98. 7 of them are nominal $1 street-space or sidewalk permits. 9 expired or cancelled permits are not shown.
Nearby
- Marland Hotel Same street
- 501–507 Geary Street Same street
- Kaiser Channel 44 KBHT T.V. Studio Same block
- 445 Geary Street Same block
- Geary Theatre Same block
- 401–405 Geary Street Same block
- 501 Taylor Street Around the corner
- 70 Derby Street Around the corner