37.7241, −122.3978 A locator map appears here once a Mapbox token is configured.
Know This Place

District 10 · Block 5431A, Lot 001G · ZIP 94124

200–202 Paul Avenue

Industrial building · Bayview Hunters Point

  • 5 stories
  • 439,294 ft2
  • 236,391 ft2 lot area
  • 4 residential units
  • 21 rooms
  • 13 bathrooms
  • Zoned PDR2
  • Historic resource
  • Sold November 12, 2004
Land$52,921,728
Improvements$77,658,472
Total assessed$130,580,200
37.7241, −122.3978 Street View appears here once a Google Maps embed key is configured.
  1. 1955

    Built.

  2. Mar 1984
    Permit 8402357 $$$ $10,000

    Interior demolition, knock out for new openings.

  3. Feb 1999
    Permit 9903140 $$$ $4,000,000

    Construct new partitions, installation-electricl & hvac.

  4. April 22, 1999

    The City Planning Commission approved with conditions conditional use authorization to install twelve receive-only parabolic antennas on the roof of the building and three monopole antenna towers attached to the north side of the building, 6-0.

    San Francisco City Planning Commission minutes, San Francisco Public Library (Internet Archive)
  5. Mar 2000
    Withdrawn Permit 200003104093 $$$ $4,800,000

    Additions alterations or repairs.

  6. May 2000
    Permit 200005089319 $$$ $900,000

    Tenant iprovements 5th floor.

  7. Jun 2000
    Permit 200006172938 $$$ $3,000,000

    To erect switch station/storage.

  8. September 14, 2000

    The City Planning Commission did not take discretionary review and approved demolishing an industrial building and constructing a new approximately 87,000 square foot industrial building, 5-0.

    San Francisco City Planning Commission minutes, San Francisco Public Library (Internet Archive)
  9. September 14, 2000

    An industrial building stood on the site.

    San Francisco City Planning Commission minutes, San Francisco Public Library (Internet Archive)
  10. Jan 2003
    Permit 200301286157 $$$ $2,500,000

    Interior tenant improvement in an e underground fl of building, includes infilling 2 existing roll-u.

  11. Aug 2006
    Permit 200608179759 $$$ $4,000,000

    1st floor - tenant improvement on 1/f, new data center and electrical room.

  12. May 2007
    Permit 200705181770 $$$ $3,000,000

    Gdround floor & roof, constuct new data center, chillers on roof, new electick room, generator on seperate permit.

  13. Sep 2007
    Permit 200709102184 $$$ $125,000

    Construct new interior walls for new data center.installation of ac units mounted to the floor. installation of one new diesel generator and one diesel fuel storage tank for the generator outside of the building.

  14. Jul 2009
    Permit 200907233307 $$$ $10,000,000

    Alteration of data and electric rooms on 4th fl of building "f". replace partial roof/top mechanical/electrical equipment with new structural supports, replace (1) generator in existing generator yard. fire alarm & sprinklers under separate permit.

  15. Aug 2011
    Permit 201108122415 $$$ $2,500,000

    New battery room within existing mechanical room, new electrical room, modification to metal canopy d.a. upgrades. note: separate battery system, operation permit required from sffd.

  16. Aug 2011
    Permit 201108162518 $$$ $3,968,336

    Work occurs on partial existing 4th floor, interior improvement includes non bearing partitions, raised access floor, ceilings, mechanical, electrical, plumbing and fire protection.

  17. Apr 2014
    Permit 201404173555 $$$ $5,300,000

    1st and 2nd floor: t.i. for electrical rooms. new data center area, common area, electrical support area, new concrete pads for generators, installtion of 2 new generators.n/a for the maher ordinance #155-13.

  18. Feb 2016
    Permit 201602190117 $$$ $5,000,000

    New data center tenant suite (d260) with supporting equipment rooms & ups rooms. improvement to new walls, doors, finishes & new mechanical & electrical work. exterior improvement tonew condensers & air handling unit on the rooftop, extend roof screen. generator and fuel storage under separate permit.

  19. Dec 2016
    Permit 201612144877 $$$ $4,400,000

    1st floor: ti includes demolition of non structural partitions & build back of non structural partitions; mep/ls under sep permit maher na.

  20. Jul 2018
    Issued Permit 201807174756 $$$ $6,250,000

    New data center on third floor of existing building. new walls, doors, finishes, and new mechanical, eletrical work. new condensors and air handling unit on roof.

  21. Aug 2019
    Permit 201908078160 $$$ $22,750,000

    2nd fl, building f - new data center. supporting equipment rooms & electrical rooms. new walls, door, finishes, mep work, new chiller/ahu on rooftops. generator pods for future generators and transformers.

  22. Aug 2019
    Permit 201908078167 $$$ $2,500,000

    (4) new generators with 4000 gallon belly tanks. on pads 31, 32, 33 & 34 within the generator yard.**maher n/a**.

  23. Oct 2019
    Permit 201910225221 $$$ $2,000,000

    Supporting equipment rooms & electrical rooms. improvements to consist of new walls, doors, finishes & new mechanical, electrical & plumbing work, exterior improvements of new chillers air handling units on the roof top. new generator pads. **maher n/a**.

  24. Oct 2019
    Permit 201910225215 $$$ $1,500,000

    New generators on pads 13, 14, and 30 serving suite f200 **maher n/a**.

  25. Sep 2020
    Issued Permit 202009194565 $$$ $3,000,000

    4/f suite f402 & f403: mechanical & electrical design for additional cooling requested to backup the existing system on 4/f.

DBI holds 295 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 295. 4 of them are nominal $1 street-space or sidewalk permits. 4 expired or cancelled permits are not shown.