144 Second Street
East Cut · San Francisco, CA 94105
-
1908
Built as the Bothin Real Estate Building.
-
Apr 1984
Total construction cost, mechanical & sprink. drawings.
-
Jan 1985
Fire corridor/new partitions & doors/hvac & sprinkler reloc.
-
Feb 1986
Tenant improvement including partitions & finishes.
-
Jul 1992
Remove 48' exist wall, install 24' of wall & new stairs.
-
Sep 1992
Enclose two area in floor.
-
Aug 1993
Upgrade restroom.
-
Oct 1993
27 fire sprinkler heads.
-
Oct 1993
Revision to p.a#9215595.
-
Oct 1993
Cti-1 5th floor el me.
-
Nov 1993
Upgrade present restroom @ 2 floor, to new title 24 standards.
-
Apr 1994
Renew application 9317860.
-
Sep 2001
Install new doors in an existingground floor lobby.
-
2008
Recorded in the city's 2008 survey of the Transit Center District, adopted in 2012, as a contributor to the proposed New Montgomery, Mission & Second Historic District.
-
Dec 2010
Work in vacant 5th fl: remove decorative sheetrock, remove low partiion glass blocks. remove hanging light fixtures. remove non service duct work. space to remain vacant until ti plans have been submitted in the future. no struct element to be removed.
-
Jan 2011
Removing existing awning patch and repair facade and repain 2nd st elevation.
-
Mar 2011
Work in arcade (basement) level. remove some decorative sheetrock and short height walls and carpet. space to remain vacant until ti plans submitted in the future. no structural element to be removed. work per ab 57.
-
Apr 2011
Barrier removal, disabled access upgrades at all bathrooms & front entry.
-
Apr 2011
Interior tenant improvement on partial floors 3, 4, and basement new non stuctural partitions, paint and carpet. no mep.
-
May 2011
5th floor tenant improvement - non-structural partitions for new offices & conference rooms.
-
Jun 2011
New lighting on all floors.
-
Jan 2015
Replace existing facp with the existing ms-9050ud(communicator). the ms 9050 shall now act as the main facp. existing conventional devices will be replaced with addressable devices on a like-for-like basis. maher n/a.
-
Dec 2016
Replace 1 rooftop packaged ac unit. relocate 1 compressor unit.
-
Mar 2017
Mezzanine: lighting replacement 1 existing conference room. interior window installation. interior door relocation. restroom upgrade to meet current accessibility requirements maher na.
-
May 2019
Basement: pony up existing wall at existing offices. demolition existing 3 offices and provide 2 new offices. maher n/a.
-
Aug 2019
Basement: modify fire sprinkler heads to accomodate t-bar cieling. add 4 pendent heads, replace damagned pended heads. ref t.i. pa201905241652. maher n/a.
DBI holds 32 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 32. 5 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the developer and the early tenants. Submit an update