45 Fremont Street
East Cut · San Francisco, CA 94105
-
1978
Built.
-
1978
A tower of 475 feet, completed in 1978 and known as 45 Fremont Center.
-
Jul 1981
Additions alterations or repairs.
-
Feb 2007
Lobby improvements ground level curain wall (glass) replacement, non load bearing partitions suspended ceiling and finishes. install entry/egress gate system. applicant to submit ul + manufacturer's spec cut (sheets) for entry/egress security gates in lobby.
-
Dec 2007
29th floor mdf room remodel. new 1hr partition with 60 min. doors. new mechanical system. fire safety under separate permit. new pre-action system.
-
Aug 2014
14th floor t.i. includes demolition of non-structural partitions and building new non-strutrual paritions. all mep's inluded. (building fully sprinklered).
-
Aug 2014
18th floor t.i. includes demolition of non-structural partitions and building new non-strucutral partitions. all mep's included. (building fully sprinklered). life safety separate permits. compliance with ord 155-13 not required.
-
Feb 2017
33rd floor: ti include drywall, ceilinmg, finishes, mechanical, electrical and full floor plumbing maher na.
-
Apr 2017
Partial interior t.i. 2nd floor: partial interior t.i. including non-bearing partitions, millwork, ceilings, lighting power hvac and finishes. n/a for maher.
-
Jan 2018
14th and 16th floors: t.i. to demolition and construct non-structural partitions, doors, millwork, ceilings, and finishes. mep and life safety & sprinklers on separate permit. n/a for maher.
-
Jan 2018
15th floor: t.i. to demolition and construct non-structural partitions, doors, millwork, ceilings, and finishes. mep and life safety & sprinklers on separate permit. n/a for maher.
-
Apr 2019
Selective demolition within the existing bsmt & ground fl lobby. demolition non-egress communication stair (level 2 - bsmt) plus slab infill @ level 1 & 2 (where removed). expansion of ground fl lobby include new exterior landscape in southern plaza. new store front entry, bicycle entry & basement bicycle amenity.
-
Jul 2019
Demolition of non structural partitions, ceilings and finishes construction of non structural partitions, doors hardware, and finishes, mep included n/a mehar.
-
Sep 2019
23rd floor: ti: includes demolition of non structural partitions, ceilings+ finishe. construct non- structural partitions, door/rames etc. meps included (sprinkler and life safety under separate permit).
-
Sep 2019
26rd floor: ti: includes demolition of non structural partitions, ceilings+ finishe. construct non- structural partitions, door/rames etc. meps included (sprinkler and life safety under separate permit).
-
Oct 2019
27th floor: demolition of non-structural partitions, ceilings & finishes. construction of non structural partitions, ceilings, door frames/hardware, millwork, drywallk, acoustic ceiling grid, finshes, mechanical, electrical & plmg. fire sprinkler and life safty under defered submittal. n/a for maher.
-
Nov 2019
10th floor. interior demolition & ti including mep.
-
Nov 2019
Interior demolition & ti including mep.
-
Nov 2019
3rd fl - interior demolition & ti including mep.
-
Dec 2019
24th fl-change of occupancy from b to a-2, place of assembly demolition of no structural, partitons, ceilings & finishes, addition of horizontal exit, construction of non-structural partitions, doors/frames, hardware, millwork, drywall & acoustic ceiling, mechanical, electrical, plumbing n/a maher.
-
Feb 2020
Tenant improvement on 8th fl to demolition and construct partitions, doors, millwork, glazing, ceilings, and finishes. mep, life safety as fire alarms on separate permit. breakroom/pantry non food service or storage.
-
Jul 2020
7/f -demolition and construction of non-load bearing partitions, doors, millwork, glazing, ceiling, finishes, restrooms and stowers. mep, fire sprinklers and fire alarms under seperate permit.
-
Feb 2022
34/f: demolition nonstructural partitions, doors, glazing, millwork, ceiling assembly, light fixtures/electrical to warm shell condition. restroom accessibility, new lighting/finishes upgrades. new lighting/finishes in lobby & service elevator corridor extension.
-
May 2022
13th fl: interior tenant improvement. full build out on 13th fl. new non-structural partitions, mechanical, plumbing, electrical, lighting and finishes.
-
Apr 2023
27th fl t.i. currently unoccupied. fire alarm and sprinkler and mep deferred. no exterior changes.
-
May 2023
Deferred mep for 202304286752.
-
Oct 2023
26/f-suite 2600: t.i., partial shell condition, no modification to existing rated core barriers/exterior envelope. modifications to elevator lobby, maintain smoke barrier rating.
DBI holds 767 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 767. 8 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 50 Fremont Street Same street
- 340–350 Mission Street Same block
- 50–80 Beale Street Same block
- 333 Market Street Same block
- 425 Market Street Around the corner
- 61–77 Beale Street Around the corner
- 77 Beale Street Around the corner