333 Pine Street
Office building · East Cut
-
1917
Built.
-
May 30, 1917
A building contract was recorded for a worm gear traction passenger elevator and an electric dumb waiter for a five-storey and basement reinforced concrete office building, at $5,600. B. G. McDougall was named as architect and the Otis Elevator Co. as contractor for the elevator. The owner was the Mills Estate, Inc.
-
June 13, 1917
A building contract was recorded for marble work for a five-storey and basement reinforced concrete office building, at $5,975. Benjamin G. McDougall was named as architect and the Jos. Musto Sons-Keenan Co. as contractor for the marble work. The owner was the Mills Estate, Inc.
-
June 20, 1917
A building contract was recorded for concrete and masonry work for a five-storey and basement reinforced concrete office building, at $22,670. B. G. McDougall was named as architect and Jas. L. McLaughlin as contractor for the concrete and masonry. The owner was the Mills Estate, Inc.
-
July 4, 1917
A building contract was recorded for glass work for a five-storey and basement reinforced concrete office building, at $2,349. B. G. McDougall was named as architect and W. P. Fuller & Co. as contractors for the glass work. The owner was the Mills Estate, Inc.
-
August 29, 1917
A building contract was recorded for tile for the flooring of a five-storey and basement reinforced concrete office building. Benjamin G. McDougall was named as architect and the Vitrolite Construction Co. as contractor for the tile. The owner was the Mills Estate, Inc.
-
December 19, 1917
A building contract was recorded for lighting fixtures, except in the basement and on the fifth floor, for a five-storey and basement reinforced concrete building, at $1,027.35. Benj. G. McDougall was named as architect and the Roberts Manufacturing Co. as contractor for the fixtures. The owner was the Mills Estate, Inc.
-
Jun 1982
Building use: office.
-
Feb 1991
Replace wood flower stand with metal kiosk.
-
Oct 2004
Renovation of existing main lobby incl non-stru demolition, partition, storefront, glazing&elevator.
-
May 2006
Oti-1 ground fl-el, me, ls, sp.
-
Jul 2006
Install fire sprinkler at tenant area connect to existing supply riser.
-
Jun 2009
1st & 3rd floor voluntary accessible upgrades of elevator car & misc accessible upgrade 1st & 3rd floor elevator entrance, 3rd floor restroom, providing drinking fountain & signage.
-
Jun 2009
Voluntary structural upgrade to existing building. new shear walls and microfiles. 3rd fl restrooms added under permit application 2009.06.17.0605. work is on 1st floor and basement levels. no exterior work.
-
Mar 2012
Ground floor: non-structural demolition, new non structural partitions, lighting electrical, millwork finishes. no increase in footprint. no change in occupancy or use.
-
Mar 2020
1st fl - demolition of existing partitions, ceiling, lights, millwork & associated plumbing fixtures. related accessible features to be provided under separate permit per ab-017.
-
Aug 2020
Interior work only. tenant improvement of existing interior space, with new non-bearing partition walls & cleaned up finishes.
-
Apr 2025
Ste 300: 3rd fl tenant improvement to include demolition of non structural partitions and ceiling construction o new partitions, ceiling, power and finishes. misc upgrades on e 3rd fl restroom and elevator lobby. mei, fire, life safe and fire sprinklers shall be on a sep permit.
-
Jun 2025
3/f: suite 300 - electrical power & lighting for t.i. pa 2025-0411-4189.
-
Nov 2025
4/f: t.i to include demolition of non-structural partitions and ceilings. construction of new partitions, ceiling, power and finishes. misc. upgrades at existing 4/f restroom and elevator lobby. this t.i is to be used as a market ready condition for marketing pruposes only.
-
Nov 2025
1/f suite 100: tenant improvement. change of occupancy from b to m. interior modifications involve selective demolition and construction of new non-load bearing partitions, interior door and glazing system, installation of new light fixtures, new millwork and new finishes.
-
Nov 2025
2/f: t.i to include demolition of non-structural partitions and ceilings. construction of new partitions, ceiling, power and finishes. misc. upgrades at existing 2/f restroom and elevator lobby. this t.i is to be used as a market ready condition for marketing pruposes only.
-
Jan 2026
1st fl suite 100 ref permit application 2025-1107-9210: fire sprinkler ti. relocate 44 total 44.
-
Mar 2026
2nd fl - title 24 lighting only. ref permit application 202511210186.
-
Mar 2026
4th fl - title 24 lighting only. ref permit application 202511059000.
DBI holds 41 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 41. 2 of them are nominal $1 street-space or sidewalk permits. 6 expired or cancelled permits are not shown.
Nearby
- 330–332 Pine Street Same street
- 340–344 Pine Street Same street
- Exchange Building Same block
- 301 Pine Street Same block
- "The Allegory of California" Mural Same block
- 240–250 Montgomery Street Same block
- 201 Sansome Street Around the corner
- 217–221 Sansome Street Around the corner