240–250 Montgomery Street
Office building · Financial District
-
September 21, 1983
The Board of Permit Appeals upheld the Department of Public Works and allowed the permit to erect a structure at 250 Montgomery Street to stand.
-
November 16, 1983
The Board of Permit Appeals upheld the Department of Public Works and allowed the permit to demolish the building at 240 Montgomery Street to stand.
-
1986
Built.
-
Jan 2010
Full floor tenant improvement. partial demolition of partitions. new partitions, electrical, hvac. new breakroom and plumbing. fire and mep under separate permit.
-
Jul 2010
Office ti on the 15th floor ( full floor) incl. new offices, new conference room and new finishes in the elevator lobby and through out. mep and sprinklers under separate permit.
-
Feb 2011
4th floor-t.i demolition of non structural partitions & building of new non structural partitions. all new or revised hvac, electrical, plubming & life safety work will be design build and submitted under seperate permit, full sprinklered. card readers installed as per plans.
-
Nov 2011
Building entry, main lobby & elevator finish upgrades. build-out consists of new store front entrance system at same location as existing, new lighting and finish upgrades. mep and fire life safety under seprate permit.
-
Apr 2012
Tenant improvement on an existing full floor tenant. construction of new partition, doors and finishes. mep and life safety under separate permit.
-
Sep 2013
9th floor-full floor tenant improvement to existing office space including new partitions, electrical, mechanical, plumbing, life safety, millwork & finishes. m.e.p design will be under a seperate permit.
-
Nov 2013
16th floor: new work consists of new ceiling ht. partitions, doors, frames, and hardware, new millwork, new power/data, plmg and finishes throughout. space is currently unoccupied. any mep and srpinkler upgrade will be under seperate permits.
-
May 2015
New interior comm'l t.i., new restaurant in existing restaurant shell space (vacant) includes new kitchen, scullery, dining area & 1 new ada toilet. no change to exterior, no change to structural. mep, sprinkler & life safety under seperate permit.
-
Jun 2015
1st floor: new mechanical, electrical & plmg & t-24 associated with interior restaurant renovation under seperate permit #201505055353. no change to building structure. sprnklr, lifesafety and hood fire supression under seperate permit (deferred). n/a for maher.
-
Jan 2016
10th floor: interior tenant improvement for spec office suite on 10th floor includes restroom upgrades, mep and life safety, sprinkler under separate permit.
-
Mar 2016
5th floor tenant improvement - demolition of existing partitions, millwork, ceiling & finishes in existing lobby & corridor.mep to be submitted under sep permit.
-
Aug 2016
6th floor suite 600 t.i.: demolitoinof existing partitions, millwork, ceiling & finishes, new finishes in elevator lobby, corridor & tenant space, new electrical, ceiling & light fixtures.mep deferred submittal. existing restrooms to be upgrades, finishes & fixtures equipment. n/a maher ordinance.
-
Nov 2016
G/f- minor demolition & base building improvements to g/f lobby & elevator cabs including new exterior entry finishes and new bike storage secure room in loading area. mep and fire/life safety deferred. n/a ordinance #155-13.
-
Dec 2016
Full floor 4th floor ti/spec suite: demolition existing partitions, millwork ceiling & finishes. new partitions, doors, glazing, electrical/power and finishes, existing restrooms: new finishes, equipment, lighting, mep and fire under separate permit. maher na.
-
Jul 2017
8/f- demolition existing partitions, ceiling and millwork. provide new millwork, light fixtures and finishes, new resteroom accessories, light fixtures and finishes. mep under seperate permit. n/a ordinance #155-13.
-
Jan 2018
#1400 - single floor ti - new walls, finishes, ceiling, lighting and electrical fixtures. restroom upgrades maher na.
-
Apr 2018
3rd floor- demolition of finishes & light fixtures. new partitions, doors, frames, glazing, ceiling-system, lighting, ele, tele/data and finishes. mep under sep permit. maher na.
-
Oct 2018
Tenant improvement: suite 1200 remove e partitons, doors and frames, millwork, ceiling system, lights, floor finishes. new ceiling system light fixtures, gyp bd header, glazing, frames, door/frames. 12th fl restrooms: upgrade, barrier removal, lighting and finishes. n/a for maher.
-
Apr 2021
9th fl spec suite ti: demolition of existing partitions & millwork. provide new millwork, new restroom accessories, light fixtures & finishes. mep under separate permit.
-
Apr 2021
Suite 1210, 12th fl ti: demolition of existing partitions, act ceiling & millwork. provide new millwork, act ceiling, lighting fixtures & finishes.
-
May 2022
15/f: demolition of existing ceiling height partitions, construction of new full height partitions, associated disabled access path of travel upgrades. work on the 15th floor.
-
Jul 2022
Suite 200: demolition of e doors, partitoins, ceiling and millwork, plumbing, ltg, new gyp bd partitions, ceiling, plumbing, lighting, millwork. mep design build deferred submittal.
-
Mar 2024
4/f interior tenant improvement & suite demising. scope includes non-structural partitions, new ceilings, light fixtures, office doors & frames & plumbing.
DBI holds 352 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 352. 15 of them are nominal $1 street-space or sidewalk permits. 1 expired permit is not shown.
Nearby
- 201–265 Montgomery Street Same street
- 300 Montgomery Street Same street
- Exchange Building Same block
- Mills Building Same block
- 333 Pine Street Same block
- "The Allegory of California" Mural Same block
- 340–344 Pine Street Around the corner
- 350 Bush Street Around the corner