Permit history
-
Oct 1981
Additions alterations or repairs.
-
Jul 1983
Interior alteration to existing area.
-
Oct 1987
Drywall & framing, sprklr, electrical, marble floors, doors, jambs.
-
Dec 2001
Installation of new roof mounted chillers on new structural steel support, chillers to be powered by.
-
Jan 2008
Tenant improments, build new offices and support facilities, upgrade mechanical and electrical systems. no increase in office space. life safety under separate permit.
-
Jul 2011
Install additional coding tower & piping for future cooling capacity for future ti work. cooling tower to e installed on rooftop on new structural steel framing.
-
Nov 2011
7th floor-tenant improvement of office space-new partitions & finishes. new lighting throughout.
-
Dec 2012
Ti on 6th fl, to include new men's restroom, non structural & finish upgrades. the scope of work includes architectural, mechanical, electrical & plumbing. no work to exterior. f/a and sprinkler on seperate prermit.
-
Mar 2015
9th floor: ti to existing office space. non structural partitions, demolition, doors, glazing, lighting, ele, ceiling, finishes & restrooms. maher- not req'd.
-
Jun 2015
Interior non structural demolition. new interior partitions. electrical work included.
-
Mar 2016
9th floor: partial floor interior t.i. in an existing unoccupied suite.work includes non-bearig partitions, ceilings, finishes & mep & limited structural work; maher n/a.life safety deferred.
-
Oct 2018
Interior ti including new partitions to make offices, lobby, conference rooms and lounge area of raised floor. no exterior work, plumbing work to include new single occupant rr & sinks in brea areas.
-
Mar 2019
2nd floor. demolition of non-structural partitions & ceilings, restrooms, raised flooring, portions of structural sub-floor & egress stair. construct sub-floor & stair clean up. t.i & restrooms included in phase 2. per ab-017 vacant space.
-
Jun 2019
Work includes improvements on 2nd fl - phase 2 - construction includes new lighting and restrooms, including new finishes, fixtures and accessories. maher na.
-
Dec 2019
Demolition of existing mechanical penthouse, and construction of new skylight, including structural improvements to existing curb to reamin and new repaired roofing.**maher n/a**.
-
Nov 2020
Existing ground floor lobby includes: demolition of existing ceilings, light fixtures, wall surfaces & finishes, specialty interior glazim & non-compliant common area restroom items. construction of new fixtures & accessable restroom upgrades.
-
Jun 2021
Work includes: improvements on the basement floor: demolition includes removal of non-structural ceilings, lighting & finishes. construction includes non -structural partitions ceilinfgs, lighting, finishes, & proving nw accessble showers, restrooms, & locker rooms. nw rated shafts to 3rd floor lightwell.
-
Dec 2022
2nd floor t.i. non structural partitions, structural elements, ceilings, fixtures and finishes. mep deferred.
-
Dec 2022
Mechanical, new energy recovery ventilator, 1 sound trap, 6 vrv condenser units. new electrical plumbing, new roof receptor for vrv. structural support for hvac equip.
-
Apr 2023
New mechanical, electrical and plumbing systems for office t.i. deffered submittal for building permit #2022-1219-8630.
-
Oct 2024
Roof demolition: tear off, haul, and dispose of eixsting roofing to down to structural concrete deck. prime and prepare concrete deck to receive sbs roofing. install sbs base sheet, heat welded (torch), install sbs cap sheet, heat welded (torch). install 2-ply flashings, pipe boots, termination bars.
-
Jun 2025
10 story building: reroofing remove existing roofing on floor roof down to concrete deck. install 2 ply sbs modified bitumen roofing system with title 24 complaint cap sheet. (torch down, hot work).
-
Jul 2025
Ste: 600 & 692. t.i. improvement to include demolition of non-structrual partitions & ceiling, construction of new partitions, ceilings, power and finishes. electrical, plumbing, life/safety/fire & fire sprinklers to be submitted on a separate permit.
-
Nov 2025
Interior ti @ suite 350 construction of new non-structural partitions, fixtures, millwork and finishes. demolition permit application 202510086992.
-
Aug 2026
7th floor suite #700: t.i. to include demolition of non structural partitions & ceiling. construction of new partitions, ceiling, power & finishes. fire, life safety sprinklers to be on seperate permits.
DBI holds 644 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 644. 10 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the developer, the early tenants and the date of the last recorded sale. The assessor's roll gives 1900; the city's statement on Progressive Era and early revival styles gives 1890. Submit an update