55 Stevenson Street
East Cut · San Francisco, CA 94105
Permit history
-
Sep 1983
Underpenning per plans.
-
Sep 1988
Install new flooring, sheetrock, electrical, plumb.
-
Nov 1988
Removal of carpet, garbage and debris.
-
Nov 1988
Replace existing hood.
-
Dec 1988
Install fire system.
-
Dec 1989
Ewo-s.
-
Aug 1994
Full seismic upgrade to comply umb ordinance.
-
Aug 2004
Oti-1 2nd and 3rd floor el.
-
Sep 2004
Changes pertaining to remodeling area/8 heads relocation/4 heads new /2 heads obselete total 14 head.
-
Sep 2004
Upgrade elevator controls, add elevator stop at basement; re-build exterior hoistway @ roof.
-
Oct 2004
Hvac mechanical work for the 2nd and 3rd floor medical office.
-
Jan 2005
Fire alarm sprinkler monitoring to comply with nfpa 72 for'b' occupancy see attached plans for fire sys.
-
Mar 2005
Erect sign for non electric, wall, projecting, double faced.
-
Feb 2006
Revew: 200408121414 for final only.
-
Feb 2006
Rene 200409214756, 200410298081 and 200501274178 for final inspection only no work.
-
May 2006
Renew app #200409174514.
-
May 2009
Install ansul 3.0 fire supression system ul 300 wet chemical fire system on 1st floor.
-
Jun 2010
Tie-in ansul sensor to existing building. fire system connection will be made 15' away @ addressable pull station. module/relay will be added at fire panel.
-
Aug 2024
To comply with abe 201804110289 sq ft ordinance to install accessible assistance sign and power door operator.
-
Aug 2024
To comply with accessible entry program 51-16. install accwessible assistance sign and power door operator.
Not yet documented: the architect and builder and the early tenants. Submit an update