580 California Street
Financial District · San Francisco, CA 94104
Permit history
-
Nov 1982
Demolitions.
-
Mar 1984
Drywall partitions, suspended ceilings, etc.
-
Jul 1984
Tenant improvements non structural walls, painting.
-
Jan 2008
22nd floor #2200 - new non-strucatural partitions, new acoustical ceiling grid & tile, new electrical outlets & lighting & new finishes. rework existing hvac to new layout, fire/life safety & sprinklers under separate permit.
-
Feb 2013
12th floor: construction non load bearing partitions, doors and frames, modification to associated mechanical, electrical and plmg as demonstrated on drawings. no exterior work. no hazardious material.
-
Jul 2013
21st floor-constrct interior non bearing partitions, doors & finshes. modifications to existing lighting & switching as affected by scope. refer to mep drawings. there are ada upgrades to existing restrooms. there is no exterior work. there are no hazardous materials on site.
-
Dec 2013
Suite 8000: demolition and construction of non structural partitions. partial demolition and construction of ceiling including electrical work. plumbing work at breakroom and ada upgrades at restrooms. no change in occupancy in occupancy or use.
-
Apr 2014
5th floor: t.i. for office building. modification of non-structural partitions doors, cabinets and finishes. life safety, sprinkler work under deffered submittal. n/a for the maher ordinance #155-13 incl mep.
-
Jun 2016
Arch/mep full floor ste 200 demolition of select interior partitions and millwork. construction of new conferences and phone rooms. new millwork, power/data and finishes throughout. space is currently unoccupied. fire sprinklers and alarms under separate permit.
-
Dec 2016
Lobby: minor renovation to existing building lobby. work consists of new reception desk, new screen walls, finishes, and relamping lights. electrical and fire on separate permit. no mechanical and plbmg. n/a for maher.
-
Dec 2016
7th floor: ti - including demolition of walls and existing ceiling system, new walls, electrical and ceiling finishes & life safety maher na.
-
Jun 2017
4/f- demolition of select interior partitions and millwork, construction of new conference rooms, new millwork, power/data, finishes throughout. space currently unoccupied. sprinkler system modification under sep permit maher not req.
-
Sep 2018
Reroofing.
-
Jul 2019
Tenant improvement to vacant suite. demolition and new non structural partitions, electrical, light fixtures and finishes. fire life safety, mep included.
-
Jul 2019
Tenant improvement to vacant suite. demolition and new non structural partitions, electrical light fixtures and finishes. mep included; fire life safety as reference.
-
Jan 2021
10/f: t.i. single tenant-demolition non-structural partitions and building new non-structural partitions. new and revised mep under this permit. life safety & sprinkler under sep permit. maher n/a.
-
Jan 2021
9/f: t.i. single tenant-demolition non-structural partitions and building new non-structural partitions. new and revised mep under this permit, life safety & sprinkler under sep permit. maher n/a.
-
Jun 2022
17th fl: t.i.. provide water line for ref & coffee maker. select demolition of existing non-load bearing walls & ceiling system. new walls, ceilings & lighting. modifications of electrical/lighting/hvac. pot previously approved under permit application 201904037033 & 201909161721).
-
Jun 2023
19/f: t.i. of office including demolition of non-structural partitions and ceilings, new partitions, ceiling power and finishes. maher n/a.
-
Jun 2023
19/f: mechanical and electrical work for tenant improvement, ref permit application 2023-0608-9570.
-
Sep 2023
Modification of office space. new ceilings, light fixtures, finishes. mep deferred. restroom upgrades, breakroom.
-
Oct 2024
14th fl. consist of interior demolition and construction of non-structural elements including but not limited to interior partitions, doors, & electrical outlets mechanincal, electrical and plumbing will be under sep permit, scope does not affect fixture quantiites, occ load calcs or path of travel no exterior building.
-
May 2025
20th fl suite 2000: scope consists interior demolition & construction of non structural elements including but not limited to interior partitions, doors, outlets & lighting. mechanical, electrical, plumbing and fire sprinkler plans will be submitted as separate permit.
-
Aug 2026
13/fl-ti and demolition of non structrual elements including but not limited to interior partitions doors, finishes, ceilings, lighting mep and life safety under seperate permits.
-
Aug 2026
15/f suite 1500: interior demolition & construction of non-structural elements including but not necessarily limited to: interior partitions, doors, finishes, ceilings & lighting. restroom finish & ada accessibility upgrades. mep & ufe safety under separate permits.
DBI holds 569 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 569. 10 of them are nominal $1 street-space or sidewalk permits.
The statement dates this tower 1986 on p. 43 and 1984 on pp. 128-129. Not yet documented: the developer and the early tenants. Submit an update