180 Hubbell Street
Mission Bay · San Francisco, CA 94107
-
1910
Built as the Standard Oil auto repair shop.
-
1947
Built as a Standard Oil Company warehouse and office building occupying a whole block, and an especially good example of the Streamline Moderne applied to industry.
-
Mar 1982
Demolitions.
-
Mar 1982
Additions alterations or repairs.
-
Mar 1982
Additions alterations or repairs.
-
Apr 1982
Additions alterations or repairs.
-
Jan 1990
Reroofing.
-
Jun 1991
Reroofing.
-
Feb 2000
Install wheelchair lift, toilet rooms and demising partition & stairs.
-
Mar 2000
Add fire sprinklers to new bathrooms.
-
Jun 2000
Oti-1 1/f el & ls.
-
Sep 2000
Oti-1- ground floor, el, me, l/s & sp.
-
Oct 2002
Correct n.o.v. #2002-24-754 install fence & gates at loading dock area.
-
Oct 2002
Addition: vestibule and demisingpartition with door, demolitionof existing office renew: 200009130393 abate no.
-
May 2004
Fire sprinklers additional coverage to front of building per nfpa 13.
-
Jul 2004
Hook up ansul fire system at kitchen hood.
-
Jan 2005
Interior remodel exist office space.remodel toiletrooms for ada compliance. selective interior demolition.
-
Mar 2005
Addition of fire sprinklers to offices.
-
Mar 2005
Add/relocate heads to accomadate t.i changes (mezz) replace 78 to new q.r heads. 80 ssp to new q.r.
-
Mar 2006
Proposed cellular on wheels truck installation c/w panel antennas (3 sectors) on a telascoping mast- temporary 180 days until permanent antenna installed on adj bldng - this includes a studded 6' chain link fence around the truck.
-
Mar 2006
Unmanned equipment in existing inteior room with proposed antennas mounted on proposed rooftop tower.
-
Apr 2006
Place cell wheels (cow) roof of existing structure for a temp wireless telcom facility.
-
Apr 2006
Amendment to application number 2006/03/13/6561 - proposed cellular on wheels truck installation c/w panel antenaas (3 sectors) on a single rooftop mounted antenna support structure.
-
Feb 2008
Minor office tenant improvement including existing loading dock (approx 840 sq ft). new exterior walls and windows, new interior partitions, doors, electrical, sprinkler placement modification under seperate permit.
-
Sep 2009
Erect a electric, wall, single faced, indirect new sign.
-
Feb 2010
Reroofing.
-
Apr 2018
Improvements to accessible parking and path of travel. existing ramp and stirs repair/replace to be updated ada compliant. minor interior work - new door parts area, partition at existing restroom area, replace existing sales desks with new. maher na. electrical under separate permit.
DBI holds 29 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 29. 1 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder, the early tenants and the date of the last recorded sale. Submit an update