180–186 Potrero Avenue
Mission · San Francisco, CA 94103
Permit history
-
May 1987
Brick vineer & change windows & doos.
-
Oct 1987
Revision #8705787, work-in-progress.
-
Aug 1992
Parpet bracing.
-
Jul 1994
Reroofing.
-
Sep 2007
Change of use b to s-1. install paint spray booth and related body shop equipment. provide accessible entry.sprinkler system throughout. sprinklers under separate application.
-
Oct 2007
Installation of fire sprinklers in existing building. total 94 heads.
-
Aug 2009
To obtain final inspection for work approved under permit application 200709253607.
-
Dec 2010
To obtain final inspection for work approved under permit application 200908044081 all work is complete.
-
Feb 2012
To obtain final inspection for work approved under permit application 200908044081; original permit application 200709253607; all work completed.
2 nominal $1 street-space or sidewalk permits are omitted from the timeline.
Not yet documented: the architect and builder and the early tenants. Submit an update