208 Utah Street
Mission · San Francisco, CA 94103
-
1911
Built as an industrial building, recorded as occupied by Abel Hosmer Warehouse / International Harvester Agricultural Implements.
-
1919
The southern quadrant on the Utah Street side was added.
-
Mar 2007
Tenant improvements (partition walls) to the 4th floor of an existing office building.
-
Mar 2007
Tenant improvements (partition walls) to the 3rd floor of an existing office building. note: mechanical & electrical work udner seperate permit.
-
Feb 2011
2/f - demolition of interior construction. construction of new interior partitions, doors, glazing & limited areas of ceiling. m.e.p. under seperate permit.
-
Mar 2011
Minor interior demolition. new interior walls, doors.glazing, some ceilings, break areas, restrooms, computer assembling/data room. mep and sprinklers under separate permits. change in use from b to f-1 and m. create new exit passageway as noted on plans as part of exit discharge for stair-1.
-
Mar 2011
Demolitoin of portion of existing floor structure, construction of new steel interconnecting stair.
-
Apr 2011
Demolition of existing 3 storefronts & replace with 2 new storefronts & 1 new window. new canopy at utah street.
-
Apr 2011
Ref. to permit #201102250970 & 201105132070 (arch. dwgs.) mechanical only. minimum mechanical air distribution from existing hvac, new fan coil units in 3-rooms, new chiller with pump.
-
May 2011
Fire sprinkler install 14 new pendents and 29 new uprights to accomodate new walls and tbar for tenant improvments.
-
Jun 2011
Fire alarm ti at 208 utah 1st and 2nd floors: 1 smoke det, 14 duct detectors, 7 central relays, 14 relays, 5 strobes, 6 horn strobes, 1 power supply.
-
Feb 2012
4th floor - commercial interior tenant improvement. demolition and construction of interior walls, doors, and glazing. mep & structural work under speparate permits.
-
Feb 2012
Modify e masonry wall with 3 new openings. add new design build fiber wrap reinforcing, new steel jambs, headers, and new continuous bolted steel collector angle. al work on the 4th floor.
-
Sep 2013
Partial demolition of existing interior partitions, installation of new conference rooms and telephone closet, relocation of existing lighting and installation of new lighting, new finishes, mep, sprinkler & fire alarm under separation permit.
-
Nov 2013
One unit: relocate lights and add new lights, for tenant improvement under application #201309116535.
-
Oct 2015
T.i. on 3rd floor to demolition partitions and glazing construction doors and glazing and add one new partition. mep will be submitted on seperate permit if needed. n/a for maher.
-
Feb 2018
Interior tenant imrpovement at 1st & 2nd floors including adding bathrooms, with cleaned up interior finishes.
-
Apr 2018
Return to warm shell condition, relocate 188 pendant to upright coverage. related to future demolition permit. non hi-rise full floor. ti on separate permit.
-
May 2018
Mep upgrades. non-structural work, electrical, mechanical, plumbing. ref ti# 201802272377. maher na.
-
May 2018
Interior remodel - 2nd floor only - removal of door and widening of existing door opening in existing brick wall.
-
Oct 2018
Replace existing exterior metal scissor gate at 201 potrero ave entry no interior work.
-
Nov 2018
Tenant improvement suite 300, 3rd fl: add operable partiton & structural bracing for same. upgrade restroom per 20% fule (see a0.3, form c).
-
Feb 2020
Per accessible building entrance checklist submittal (ord 51-16): - exterior sidewalk improvement at tenant entrance; - new door operator @ leveled new sidewalk.
-
Dec 2025
2nd, 3rd, 4th/f: property owner upgrade area of 1320 sq ft. demolition & replacement of e) partitions, fixtures, finishes, water fountain, data closet doors, 1 additional wc closet added to each restroom.
-
Dec 2025
Tenant improvement update of office areas on level 2-4. replacement of carpets, demolition and addition of partitions, updates to break areas and lighting updates.
-
Jun 2026
Ti update of reception area to incorporate security gates & security reception desk. installation of security turnstiles at ground floor lobby.
DBI holds 49 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 49. 6 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update