37.7941, −122.4024 A locator map appears here once a Mapbox token is configured.
Know This Place

District 3 · Block 0228, Lot 010 · ZIP 94111

560 Sacramento Street

Office building

  • 5 stories
  • 28,840 ft2
  • 5,667 ft2 lot area
  • 2 residential units
  • 23 rooms
  • Zoned C3O
  • Historic resource
  • Sold May 14, 2004
37.7941, −122.4024 Street View appears here once a Google Maps embed key is configured.
  1. 1909

    Built.

  2. Mar 1982
    Permit 8201524 $$$ $30,000

    Additions alterations or repairs.

  3. Mar 2000
    Permit 200003154416 $$$ $38,000

    Oti-2, el, me, g/f.

  4. Feb 2002
    Permit 200202159324 $$$ $150,000

    Umb upgrade. bpic.

  5. May 2005
    Permit 200505091923 $$$ $48,000

    Emergency temporary shoring.

  6. May 2005
    Permit 200505263520 $$$ $80,000

    Permanent replacement of the existing dameged basement piers ref permit application 2005/05/09/1923.

  7. Mar 2006
    Permit 200603096368 $$$ $50,000

    Hvac sysrem for core building - prepare for future t/i - building is historical registered.

  8. Apr 2006
    Permit 200604149042 $$$ $42,000

    Revision to approved permit application 2002/02/15/9324, the revised work includes elimination or existing stair to basement requiring revision to entry lobby floor framing & revised basement floor plan; substitution of steel moment frames for wood crosswalls on 2nd, 3rd & 4th floors. replacement of mechanical &.

  9. Apr 2006
    Permit 200604179164 $$$ $35,000

    New electrical an dplumbing systems.

  10. Nov 2006
    Permit 200611288589 $$$ $60,000

    Rough in fire sprinkler and fire service. installation of new sprinkler system through-out building with new 6" fire service.

  11. Dec 2006
    Permit 200612069259 $$$ $102,000

    Retail space fit out for barbershop. mep. is design/build under seperate permit, sprinkler under seperate permit.

  12. Feb 2007
    Permit 200702214602 $$$ $80,000

    Revision to approved app #2002/02/15/9324 remove existing elevator cab and install new elevator cab in existing 1-hr rated elevator shaft patching and repairing of existing 1-hr rated stair shaft walls to remain.

  13. Dec 2007
    Permit 200712261312 $$$ $450,000

    Office tenant improvement on 4th fl. work includes non bearing wall for it room, millwork counter & cabinetry, flooring, painting and electrical. converting power to new and relocated light fixtures, power outlets & tenant equipment. mechanical. work to include ducting, new heat pumps & exh.fans. int.work only.

  14. Aug 2009
    Issued Permit 200908174944 $$$ $50,000

    Reconfiguration of entry to provide accessible means of access to 1st floor. structural work to accommodate revised entry; reconfiguration of existing restrooms to meet accessibility requirements.

  15. Aug 2009
    Permit 200908195134 $$$ $315,000

    Construction of non-bearing walls to demarcate offices & conference rooms. new millwork counters & cabinetry, new flooring & painting. electrical work to be include power & lighting changes. mechanical work to incl. ducting & new heat pumps.

  16. Sep 2009
    Permit 200909096416 $$$ $115,000

    New basement egress stairs with structural drawings & calculations. no mechanical, plumbing. electrical & sprinkler under seperate permit.

  17. Jul 2010
    Permit 201007025896 $$$ $300,000

    3rd floor office ti full build out, select demolition of walls, ceiling, lighting, construction of new walls, finishes; new stair connecting 3rd to 4th floor; new millwork. new lighting, electrical, plumbing and mechanical. fire sprinklers under a separate permit.

  18. Aug 2011
    Permit 201108162549 $$$ $68,000

    Basement tenant improvement 1700 sq ft: new restrooms & minor non-structural tenant improvements for partitions, lighting & plumbing., mep & sprinkler under separate permit.

  19. Jun 2012
    Permit 201206011716 $$$ $12,000

    1st and 2nd floor: construction of non bearing partition walls and hard lid ceilings in approx 670 sq ft of existing office. electrical work to include connecting power to new or relocating lighting fixtures, power outlets and require mechanical title 24 work under separate permit.

  20. Nov 2012
    Permit 201211083866 $$$ $100,000

    Construction of non bearing paritions walls and hard lid ceilings in 600 sq ft of existing office space. new lighting. reconfigured kitchen. upgrade restroom to ada compliance.

  21. Nov 2012
    Permit 201211144191 $$$ $50,000

    Construction of non bearing partition walls and hard lid ceilings. new lighting, title 24 calcs included.

  22. Nov 2015
    Permit 201511182899 $$$ $57,000

    3rd fl ti to existing office space approx 600 sq ft replacement of existing glazing system and enclosing 1 existing open meeting room. no structural work or change of use. mep, life safety under separate permit if req.

  23. Apr 2018
    Permit 201804186677 $$$ $360,000

    Tenant improvement at basement level to demolition and construct partitions, doors, finishes, lighting power systems. sprinklers, life safety separate permit maher not req.

  24. May 2018
    Permit 201805078362 $$$ $44,925

    T-24 mechanical to install new mechanical systems on basement level ref 201804186677 maher na.

DBI holds 77 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 77. 12 of them are nominal $1 street-space or sidewalk permits. 1 expired permit is not shown.