130 Townsend Street
South Beach · San Francisco, CA 94107
-
between 1947 and 1951
The Office of the Assessor-Recorder photographed the property for tax assessment.
-
July 28, 1975
The Office of the Assessor-Recorder photographed the property for tax assessment.
-
Jan 1982
Additions alterations or repairs.
-
Feb 1982
Additions alterations or repairs.
-
Aug 1982
Additions alterations or repairs.
-
Mar 1993
Reroofing.
-
Jul 1998
Reroofing.
-
Sep 1998
Non-electrical wall sign.
-
Jun 2000
Tenant improvement include conference room, office, enlarge kitchen, disable access toilet, partitions.
-
Dec 2004
Interior non-structural demolition only. ada/t-24, work to be done with t.i.
-
Jan 2005
Market improvement alterations to existing space work includes new non structural interior partitions.
-
May 2005
Installation of new commercial fire sprinkler system. 25 heads.
-
May 2005
Alterations to building. facade, interior t.i. including non-structural interior partitions, h.c.accessibl.
-
Oct 2005
Hook up fire suppression system.
-
Oct 2005
Install new fire alarm system, 11 horn strobes, 5 smoke dect, 2 pull stations.
-
Dec 2005
Erect sign for electric, double faced.
-
Mar 2015
Restaurant renovation limited to the transformation of service space into small kitchen and the creation of new bar. no new lighting and no modification to the envelope. plumb & ele under seperate permit. maher - not req'd.
-
Apr 2015
Renovation of exhibition space to create new storage mezzanine and reconfigure storage and office space on ground floor. n/a maher.
-
Jul 2015
Install ul 300 fire system. ref app#201503049990. n/a for the maher.
-
Jul 2015
Add 1 monitor module to monitor new ansul system.
-
Feb 2021
Construct a 6 story office building on the existing surface parking on the north side of the property (50 stanford).
-
Feb 2021
Adaptive re-use of existing age eligible building in a historic district to retain existing facade & build a 5-story vertical addition, resulting in an office building with ground floor retail/restaurant use. the proposed office will be under the.
-
Jul 2022
Temp lateral support to facilitate mass excavation at 130 townsend. soil nails and shotcrete facing. soldier piles, raker bracing, and shotcrete facing. shoring soil nails, shotcrete, and soldier piles will not extend beyond the project property lines, into city streets, or adjacent properties.
-
Jul 2022
Temp lateral support to facilitate mass excavation at 130 townsend aka 50 stanford. soil nails and shotcrete facing. soldier piles, raker bracing, shotcrete facing. shoring soil nails, shotcrete, soldier piles will not extend beyond the project property lines, into city streets, or adjacent proper.
-
Nov 2022
Vapor intrusion mitigation system.
-
Nov 2022
Vapor intrusion mitigation system.
DBI holds 35 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 35. 1 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update