246–250 Kearny Street
Union Square · San Francisco, CA 94108
Permit history
-
Dec 1982
Additions alterations or repairs.
-
Oct 1983
Additions alterations or repairs.
-
Jul 1984
Bring building into compliance with code.
-
May 1991
Remove old roofing/instant new flashing new gravel.
-
Oct 1997
Reroofing.
-
Dec 2001
Compliance with notice of violation #200006517 only under this permit.
-
Jan 2002
Umb/seismic retrofit work.
-
Aug 2003
Sro 170-03 sprinkler system compliance - complaint #200235900 per plan.
-
May 2004
Response to n.o.v#200006517, access at popol restaurant. revise permit app#9705472 harde place entry.
-
Jun 2006
Roof plywood and steel frames-renew permit application 2002012878530-per inspection from umb inspector. to continue work & obtain final inspection.
-
Jan 2008
Ren permit application 200606224789 to continue work.
-
Feb 2009
Minor cosmetic (i) work to remove vinyl floor & refinish wood floor underneath; replace formica bar counter-tops with walnut & finished; remove existing storage shelves from front bar.
-
May 2009
Renew 200201287853/r1. to complete work and obtain final inspection for work approved under 200201287853/r1.
-
May 2009
Sidewalk repair new topping slab.
-
Dec 2010
Comply with nov#201060593. repair/replace doors, windows, plumbing & electrical fixtures, heating, fire escapes, door hardware, damaged walls, handrails, alarm system, repair elevator. all his nov's & ces nov restore community kitchen next to #105 to guest room.
-
Jul 2011
Reconfiguring of rooms on all floors including creating of community kitchen & accessible bathrms. reducing # of rooms from 145 to 136 & increasing # of bathrms. from 110 to 131, structural work address all outstanding complaints & nov's; 200005134 & 201061908.
-
Jul 2011
To obtain final inspection for work approved under permit application 200905118129. all work is complete.
-
Sep 2011
Installation of a new fire alarm system, sprinkler monitoring, smoke detection in hallways, heat detector laundry room and elevator recall in exisiting low rise r-1 building- no pull statioins required at exits- complete building evacuation.
-
Mar 2012
Replacing 35 windows at rear & 24 windows facing hardie place with dual glazed fiberglass windows.
-
Jan 2014
Demolition existing sidewalk & construction of new sidewalk including replacement of existing steel beams to abate ntr #996343 issued by dpw.
-
Jun 2014
New entry store front to residential lobby. replace upper floor windows.
-
Nov 2015
88 hardie pl: repair kitchen floor finishes approx 900sf to meet dph requirement. and add 2 new floor drains & 2 floor sinks.
-
Feb 2017
Voluntary installation of (59) non-accessible proivate bathrooms @ non-accessible units, installation: (1) 48" grab bar @ tub back/(1) 24" gb @ tub control; (1) 24" gb @ toilet rear/(1) 42" gb @ toilet side. grab bars =1-1/4" dia, 25016 load capacity. assist bars @ units: 211, 212, 214, 218, 219, 220, 221.
-
Mar 2022
Emergency evacuation maps/signs (29) for fire only permit.
-
Dec 2022
Installation of canvas awnings over store front.
DBI holds 59 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 59. 9 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the architect and builder and the early tenants. Submit an update