112 1st Street
Office building · East Cut
-
Aug 1983
Erect.
-
Sep 1984
Demolition.
-
December 4, 1985
The Board of Permit Appeals upheld the Department of Public Works and allowed the permit to demolish the building at 112-114 First Street to stand.
-
1988
Current structure built.
-
Jan 2001
Remove 9 lf of storefront, at suite 100 install new wall/door & 2 atm's.
-
Sep 2006
Add 1 asprinkler head and relocate 1 existing head for new door location - door under separate permit this permit: sprinkler work.
-
Apr 2007
Oti-1, 7th floor, sp, ls.
-
Dec 2007
17th floor - commercial office tenant improvement on the 17th floor. walls, doors, ceiling. work on accessible restroom under seperate permit. mep - defered submital.
-
Jun 2009
To obtain final inspection for work competed under permit application 200804290851, all work has been completed.
-
Jun 2009
To obtain final inspection for work competed under permit application 200709253646, all work has been completed.
-
Jun 2009
To obtain final inspection for work competed under permit application 200709253642, all work has been completed.
-
Oct 2010
To erect an electrical, aluminum back ground with new an illuminated cabinet at the top of the new back ground.
-
Mar 2012
Ground floor fire sprinkler work - relcoate the fdc's on the n.w. & s.e. corners, relcoate 1 & add 1 pendent sprinkler.
-
Nov 2012
Fire sprinkler system upgrade, relocate 6 pendent sprinkler heads on the 13th floor, relocate 34 sprinklers upright. add 3 pendent sprinkler heads and delete 5. t.i. permit application 201208238099.
-
Jan 2013
Create & produce 3 evacuation map signs on 1st fl.
-
Dec 2014
12/f - partial floor tenant improvement including selective demolition, partition, ceiling finishes, electrical, mechanical, plumbing. sprinklers and life safety sep permit.
-
Jan 2020
Accessibility improvements to the restrooms on the 12th fl. scope of work includes barrier removal only deferred mep life safety fire sprinklers fire alarm.
-
Jan 2020
Accessibility improvements to the restrooms on the 16th fl. scope of work includes barrier removal only deferred mep life safety fire sprinklers fire alarm.
-
Jan 2020
Accessibility improvements to the restrooms on the 17th fl. scope of work includes barrier removal only deferred mep life safety fire sprinklers fire alarm.
1 nominal $1 street-space or sidewalk permit is omitted from the timeline. 1 cancelled permit is not shown.
Nearby
- 110 1st Street Same street
- 116 1st Street Same street
- 100 First Plaza Same block
- 118 1st Street Same block
- 519 Mission Street Same block
- 22–525 Mission Street Same block
- 512 Mission Street Around the corner
- 415 Mission Street Around the corner