Langley and Michaels Building
42–50 1st Street
-
1917
Built as the Langley & Michaels Building, a masonry commercial loft.
-
Aug 1984
Demolition of non structural walls.
-
Dec 1985
Modify exist. g/f space for use as post office facility.
-
Mar 1987
Non bearing walls, toilet & shower rooms, electrical outlets.
-
Jan 1988
Construct tenant partitions, demising walls for ste #303/312.
-
May 1988
Construction of interior corridor & tenant partitions.
-
Jun 1988
Construct interior gyp bd. walls, demising 3 suites.
-
Nov 1989
Tenant improvements-partitions, sheet rock and paint.
-
Feb 1992
Remodel.
-
Mar 2001
Install & enlarge restroom, wall finishes, new dining room image enhancement.newcarpet, floor coverin.
-
Apr 2002
Oti-1 2nd floor, el, me.
-
May 2002
Oti-2, 2nd floor, ltg, mechanical.
-
May 2002
Oti-1 2nd floor ltg, mechanical.
-
2010
Counted in 2010 among the four buildings of the First and Mission Historic District — a district not formally listed but found eligible for the California Register, and identified in the Transit Center District Area Plan Survey — all four of which stood on the site proposed for a three-tower development. Seven storeys of offices and shops.
-
Oct 2015
To erect 60 stories, 4 basement, type ia, 109 units residential, office, retail building.201903215849.
-
Mar 2016
Asbestos abatement and related soft demolition. removal of flooring, interior walls and ceilings, pipe insulation and roofing.
-
Apr 2016
To demolish 7 stories, office / retail building.
-
Mar 2017
Cutter soil mix (csm) wall for tower 1.
-
Aug 2017
Bracing and excavation for new building approved under permit application 2015-1030-1303s. (csm wall installation under seperate permit #2017-0303-0650).
-
Jan 2018
Revisions to tower 1 csm wall approved under permit application 2017-0303-0650.
-
Jun 2018
Temporary construction trestle to support construction approved under appln #201510301303-s.
-
Apr 2019
Errect 2 temporary tower cranes for construction of new building approved under permit application 2015/10/30/1303-s.
-
May 2019
Installation of 2-8 inch fire service on stevenson street maher not req.
-
September 17, 2026
Oceanwide Center No More, Renderings Revealed For Fifty at First, San Francisco — San Francisco YIMBY
-
October 13, 2026
Formal Application For 56-Story Tower at Fifty at First, San Francisco — San Francisco YIMBY
DBI holds 120 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 120. 10 of them are nominal $1 street-space or sidewalk permits. 4 expired permits are not shown.
Nearby
- 36–40 1st Street Same street
- 62 1st Street Same street
- 25 Jessie Street Same block
- 76–78 1st Street Same block
- 82–84 1st Street Same block
- 516–520 Mission Street Same block
- 455–475 Market Street Around the corner
- 440–456 Mission Street Around the corner