130 Bush Street
Financial District · San Francisco, CA 94104
-
1910
Built.
-
1910
Heineman Building, designed by Kenneth MacDonald Jr. and George Adrian Applegarth.
-
1910
The building was up by 1910, and was the only structure in the blocks around Market and Battery Streets listed for its architectural importance in A Guide to Architecture in San Francisco and Northern California (1973).
-
Apr 1988
Replace ground floor marble work.
-
Mar 1991
Existing 1200 sq ft. open area demolition t-bar ceiling.
-
Sep 1991
Tap existing risen & size new pipe to new sprinkler.
-
Sep 1991
Install partition, new doors, paint & plaster.
-
Jan 1992
Repair fire damage.
-
Sep 1995
Refurbish existingrest.kitchen & instll h/c toilet.
-
Dec 1995
Put in duct work & install hood.
-
Feb 1996
Hook-up of pyro-chem, hood fire suppression system(9514770).
-
Jan 1997
Install fire escape ladder from mezzanine to street level.
-
Aug 1997
Renewal permit applications #9514770/9701377.
-
Feb 2004
Add two smoke detector to exist fire alarm system for elevator recall.
-
Jan 2007
Abatement of notice of violation #200672058 on 6th floor only ( no plumbing and mechanical) and #200843116.
-
May 2009
Fire sprinkler work only. replace partial sprinkler system with new fire sprinkler to protect the entire 6th. floor. per approved building application#2007/0118/1975. (23 heads total).
-
Oct 2009
Caulk vertical expansion joint at 130 bush st. 3 in wide.
-
Aug 2011
Fire alarm upgrade - new equipment, 1 facp, 1 ra, 11 smokes, 7 pull stations, 12 horn / strobes, 4 strobes, 12 modules, 1 voice panel, 1 distribution panel, & 12 jacks.
-
Apr 2012
Replace existing fire alarm panel with new addressable panel to accommandate new fire pump. existing equipment to be replaced like for like at their original location. this is phase one to upgrade the entire building to code.
-
Feb 2013
To obtain final inspection for work approved under permit application 200905148446 all work is complete.
-
Jun 2013
Obtain final inspection for work approved under permit application 2007-0118-1975. all work is complete.
-
Jan 2015
6th fl: to comply with complaint #201412022 - demolition of partition walls, remove illegal massage back to open office use. n/a maher ordinance.
-
Apr 2015
6th floor: plug 3 fire sprinkler heads.
-
Sep 2016
New partition wall. select disabled access upgrades. sprinklers under separate permit.
Nearby
- 100–120 Bush Street Same street
- 200 Bush Street Same street
- 100–130 Sansome Street Same block
- 140–142 Sansome Street Same block
- 235 Pine Street Same block
- 160–180 Sansome Street Same block
- 2–22 Battery Street Around the corner
- 98 Battery Street Around the corner