Shreve Building
200–210 Post Street
-
1903
Louis Mastropasqua, then in William F. Curlett's office, assisted with the design.
-
1905
Built.
-
1905
Shreve Building, designed by William F. Curlett.
-
July 4, 1907
A builder contracted for window frames and doors on an eleven-storey and basement class A building for the Crocker Hotel Company, at $6,003.
-
1918
Shreve and Company jewelers, named in 1918 court-martial testimony as a downtown gathering point.
-
May 1999
Interior remodel provide shelfing and wall.
-
Jun 2000
Retail stores remodel per plans.
-
Jun 2010
Kate spade. ground floor. minor lighting and flooring, replacement for existing retail store. no exterior work.
-
Jun 2010
1st floor-relocation of existing display cases, new wood wall panel system on west wall, alteration of existing display cases. all work to be done on 1st floor only.
-
Dec 2014
Interior renovation of existing retail space work includes finish changes, new non-structural partitions, new structural mezzanine, new minor mechanical duct relcoations, new electrical & lighting. no change to exterior. signage under separate permit.
-
Feb 2015
Interior renovation of existing retail space, work includes finish changes, new non structural partitions, new minor mechanical duct modifications, new electrical and lighting, new signage to be under separate permit.
-
Jul 2015
Interior non-structural demolition to remove previous ti in advance of a new ti. new walls, floors, fixtures, lighting, mep & finishes.
-
Jul 2015
New storefront system at ground level, new signage for new t.i.
-
Aug 2015
Installation of security camera, awning, and new ventilation grate; removal of security gates; removal of door on grant ave, r&r 1st floor storefront windows, paint removal, repair and paint window frames, repair and refinishe wood trim & brass finish around post st entrance.
-
Sep 2016
Replace existing toilet fixtures, partitions, and sinks. barrier removal at bathrooms on floors 2 to 11.
-
Jun 2017
Upgrade & modify existing basement fire sprinkler system, replace existing firepump and extend system to protect ground floor.
-
Jun 2017
Revision to bpa 2015-0727-2539 interior work only; redesign basement level.
-
Jul 2017
Add 61 new smoke det add 1 new heat det, 1 new power spuply 6 new pull stations, 18 control relays for heat pumps shutdow full area notification, sub, ground, mezza floors.
-
Nov 2017
Revision to 201706088809, to replace pump per app#201706088809. t.i. ref app#201507272539.
-
Feb 2018
Title 24 for permit application 201609228486.
-
Mar 2018
Revision to 201609228486, change from 2 ada baths on each floor to 1 on each floor.
-
Sep 2018
Revision to pa 2018-0322-4364. 2nd floor only: 1 ada bathroom &1 gender neutral non-ada. 11th floor only: women's bathroom ada-toilet.
-
May 2019
Adding lighting and gfi outlets forrestroom remodel on 2nd & 11th fl.
-
May 2024
Ground floor: interior renovation of existing demiseo retail space.
DBI holds 74 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 74. 15 of them are nominal $1 street-space or sidewalk permits. 5 expired permits are not shown. The assessor's roll gives 1905; this address is recorded as built 1903.
Nearby
- 185 Post Street Same street
- 201–209 Post Street Same street
- 220–222 Post Street Same block
- 228–240 Post Street Same block
- 231–233 Grant Avenue Same block
- 239 Grant Avenue Same block
- 118–120 Maiden Lane Around the corner
- 220–288 Grant Avenue Around the corner