220–288 Grant Avenue
Financial District · San Francisco, CA 94108
-
1908
Built.
-
1908
Phoenix Building, designed by Kenneth MacDonald Jr. and George Adrian Applegarth.
-
Apr 1982
Additions alterations or repairs.
-
Oct 1983
Additions alterations or repairs.
-
Apr 1984
Basement alterations.
-
Jul 1986
Remodel of approxi.625 sq ft. of retail space.
-
Mar 1988
Install new non bearing partitions, sheetrock.
-
Apr 1990
Seismic upgrade structural rmedial work.
-
Apr 1991
Construct floor in abandoned stair opening.
-
May 1991
Remodel existing lobby.
-
Jun 1991
Add of 7 dressing rms., reconfiguration of front entry.
-
Jul 1991
Store front to be install.
-
May 1998
Remove non bearing wall at basement & g/f intall hd chnge rm.
-
Jul 2004
Site permit-to include storefront alteration and commercial tenant improvement.
-
Dec 2004
Tenant improvement of 6th floor. provide mirror at back of elevator cab for upgrade.
-
Jan 2005
Supplement to app #200407088294 removal of columns to be replaced with beams demolition and infill of slab.
-
Feb 2006
Remodel ground floor entrance lobby new flooring and finish work. new black painted ribbed glass panels on partial facade. all signage under sep permit. all non structural.
-
Aug 2008
T.i. at ground floor: interior non-structural remodel of existing retail space, no exterior, sprinkler & fire alarm under separate permit. new store front under seperate permit.
-
Aug 2008
New storefront for ground floor retail space.
-
Apr 2009
T.i.: on 5th. floor. consisting only of barrier removal to bring area of remodel to ada accessibility compliance, adding new 2nd. bathrm. to meet accessibility requirements for 1-male & 1-female accessible fac. coffe area, sink & cabinets, also to remodeled & are ada accessible.
-
Jul 2012
Install one new fire-ton capacity split system heat pump and all new supply return and outside air ducting.
-
Oct 2016
4th floor: add 1 ada accessible restroom. remodel kitchen/breakroom and existing restroom.
-
Mar 2019
Tenant interior improvements for level 2 & 3. minor wall modifications, and cleaned up finishes. maher n/a.
-
Apr 2019
Ti - ground floor and mezzanine non structural work to include new finishes, interior partitions and lighting/ele.
-
Aug 2022
Structural repair of ground floor slab supports in limited basement area. new hss beams and existing concrete beam rapir.
-
May 2024
6/f: tenant improvement. relocate partition walls. new outlets. new lobby doors.
DBI holds 92 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 92. 3 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 164–166 Grant Avenue Same street
- 231–233 Grant Avenue Same street
- 170–190 Post Street Same block
- 150 Post Street Same block
- 255–271 Sutter Street Same block
- 126–130 Post Street Same block
- 185 Post Street Around the corner
- 200–210 Post Street Around the corner