150 Post Street
Financial District · San Francisco, CA 94108
-
May 1982
Additions alterations or repairs.
-
Oct 1985
Partitions.
-
Apr 1988
Tenant improvement, bsmnt, ground, 2nd floor.
-
Jul 1988
Tenant improvement.
-
Oct 1998
Seismic upgrad umb.
-
Jan 2000
Site permit/scope tenant.
-
Jan 2000
Tenant improvement-upgrade existing elevator cab & add additional stop at mezzanine level.
-
Dec 2000
Oti-1=me, ls, sp 5th fl only.
-
Jan 2002
Corridor & restroom upgrade for fls e, r & e. restrms will be brought to full compliance. corridor w.
-
Oct 2002
Lobby remodel-finishes, lighting, elevator lab finishes, sidewalk upgrade-entry slope.
-
Oct 2002
Corridor & restrm upgrade on floors 3, 4 & 6; finishes & light at corridor, complete restrm upgrade.
-
Feb 2004
#740- office t.i., electrical, mechanical. no structural work. no exterior work. fire sprinklers under.
-
Aug 2004
Revision to approved seismic upgrade umb permit#9821899.
-
Dec 2004
Tenant improvement on portion of suite 405 - non structural partitions under grid.
-
Jul 2005
Interior remodel of existing retail space on basement, 1st & 2nd floors. partial slab infill on.
-
Aug 2005
Replace boiler.
-
Aug 2006
5th floor, suite 500 - demolition interior walls per plan - build new walls to create new offices reception area, break room, relocate lights on 5th floor.
-
Apr 2007
Seismic upgrades at elevator walls, terra cotta wall stabilization. no architectural improvements.
-
Oct 2015
Basement: replace hvac water chiller. installation of refrigerant monitor.
-
Dec 2015
Interior t.i. of an existing retail store. add a convenience stair. all other work under separate permit. signage, fire protection, storefront, mep. under seperate permit.
-
Jul 2016
Demolition non-structural 9e) walls. alteration and expansion of current suite 320 to suite 310 & 335. fire sprinklers and life safety device modification by design build. 20% ada compliance.
-
Mar 2018
Demolition of a switchback communications stairs btwn 1st/2nd. infill 2nd floor opening slab and stair opening. modification of vacant space to include selective demolition and construction of non load bearing partitions.
-
Apr 2018
Modification of existing tenant improvmens to include selective demolition and construction of non load bearing partitions, existing modification to gypsum board ceiling, new light fixtures, new switche, new office doors and frames, salvage and reuse of existing selected materials if practicable, millwork.
-
Feb 2020
Suite 700; interior tenant improvement only, including new partitons, doors, flooring, ceilng and mep.
-
Jun 2024
At gr floor: modification of existing tenant space to health spa. to include selective demolition, construction of non load bearing partitions. new office door, frames, millwork, new sinks, finishes. mep deferred.
-
August 2026
Union Square Tower Slips to Lender as $73.6M in Debt Goes Unpaid — Hoodline
DBI holds 310 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 310. 4 of them are nominal $1 street-space or sidewalk permits.