1911
A wood and metal warehouse was built for the Dyer Brothers Iron Works, which stayed until 1935.
-
1935
Fraser and Johnson Gas Furnace and Metal Products took the site over from the Dyer Brothers Iron Works and held it until 1972.
-
Mar 1990
Excavate.
-
September 1998
The warehouse, latterly a solid-waste recycling and transfer station, and the two-storey office building with it were both vacated.
-
Mar 2000
Erect a four story office/parking/retail building.
-
Mar 2000
Shoring/excavation.
-
2002
Built.
-
Apr 2004
Install new t.i. for california culinary academ & install teaching kitchens, class room etc.new exter.
-
Oct 2004
Phase 2 of permit application 2004/04/09/0900. partitions for resturant on 1st floor. class room on 2nd floor & 3rd.
-
Jul 2006
Oti-1, 1st floor, el, ls, sp, me.
-
Aug 2006
Oti-2 1st/fl, el-me, sp.
-
Feb 2008
Tenant improvement to provide new office space and open work area in an existing shell space. new acoustical ceiling tile and grid. mechanical, electrical, structural work included.
-
Jun 2008
3rd floor-build out of 7500 sq ft of new office space, reconfigureation of 8389 sq ft of existing office & classroom space for an existing cooking school. work confined to 3rd floor. fire sprinkler & alarm under seperate permit.
-
Feb 2010
Ti 3rd floor: build out new 12, 250 sq ft space. paint, carpet, walls, reconfig ex 8358 sq ft: remove walls, carpet, vct, doors, sidelites, reinstall.
-
Mar 2010
3rd floor m.e.p. work, refernece arch permit application 2010/02/23/6970.
-
Jul 2012
2nd floor-tenant improvements including new construction of partitions, doors, and sidelights, new finishes, new electrical, and new relocated lighting. no structural work. mep and title 24 under separate permit.
-
May 2013
2nd floor #220 (show place square #2185) - t.i. office space & breakroom including new floors, wall finishes, new partitions, base utilities, m.e.p. sprinklers under separate permit.
-
Nov 2015
3rd fl: project consists of selective demolition of partitions, doors frames, power, ceiling, lighting & finishes. construction of new interior tenant partitions, doors/frames, power, data, ceiligh/lighting and finishes. suite is curently unoccupied. life safety, mechanical, electrical, plmg and sprinkler.
-
Aug 2018
4th floor. interior minor demolition of non-structural elements. construction of new conferences, training, offices, pantry / break room and record room. life safety and sprinkler plans will be submitted as separate permit. maher n/a.
-
Jan 2019
3/f: interior demolition of non-structural elements. cosntructuion of new conference rooms, offices, file rooms, pantry and restroom. life safety and spirnkler will be under sep permit. maher n/a.
-
Jan 2019
2/f: interior minor demolition and cosntruction of new conference room and offices. life safety and spirnkler will be under sep permit. maher n/a.
-
Sep 2020
1st fl: interior demolition at non-structural elements. construction of new conferences, meetings, offices, and pantry. upgrade 1st fl restrooms to be compliant. mep, left safety, furniture, av and security to be separate submittal. path of traval approvaled per permit application 201901150438.
-
Sep 2020
Interior demolition at non-structural elements. construction of new conference, offices, meeting rooms, & pantry, existing restrooms are compliant. mep, life safety, furniture, av & security to be separate submittal. path of travel approved per permit 201901150438.
-
Sep 2020
3rd fl: interior demolition at non-structural elements. construction of new conference, offices, existing pantry to remain, existing restrooms are compliant. mep, life safety, furniture, av & security to be separate submittal. path of travel approved per permit 201901150440.
-
Oct 2021
Suite 220: consist of interior demolition of non-structural elements including but not necessarly limited to interior partitions, doors finishes, ceilings, lighting, mechanical & electrical outlets & switches.restroom ada accessiblitiy upgrades.
-
Nov 2021
Addition of roof deck & elevator extension to roof of an existing building - applicant has removed the proposed 12 foot tall pergola as of 11/5/2021.
-
Nov 2023
2/f-ste# 220/230: interior demolition at non-structural partitions and millwork. new interior partitions at breakroom, finishes and relocate at workstations. lighting & power, mep, life safety, and sprinkler under separate permit.
-
Jul 2024
Ste #250: remodel e) medical space on 2nd fl to expand e) out patient modical office suite.
-
Jul 2026
3/fl- construction of new full height non load bearing paritions, doors, glazing millwork, finishes, plumbing, associated electrical power lighting distruction associated mep and fixtures.
DBI holds 223 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 223. 8 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 251–275 Rhode Island Street Same street
- 375 Rhode Island Street Same street
- 300 De Haro Street Around the corner
- 1616 16th Street Around the corner
- 1830 17th Street Around the corner