111–121 New Montgomery Street
East Cut · San Francisco, CA 94105
-
1907
Built as the Standard Building.
-
Apr 1983
Additions alterations or repairs.
-
Nov 1983
Installation of fire sprinkler system.
-
Feb 1995
Seismic upgrade to general proceedures & handicap upgrade is.
-
Jun 1995
Retail tenant imprvt with new storefrnt & full handicap.
-
Oct 1995
Ti on ground floor, a/c access under appl #9508630.
-
Dec 1996
Alter the interior partition on existing deli.
-
Oct 2000
Construct new wall partition. install gas pipe & plumbing lines, electrical outlets, fire sprinkler.
-
Feb 2001
Install new exhaust hood, duct, exhaust fan, make up air one unit/31/4534.
-
Apr 2004
Install 3 new ranges with existing make up air & exhaust system.new millwork & electrical &plumb on 1st fl.
-
Apr 2007
Remodeling portion of convenient store to add juice bar. 78 sq ft. approximateley to add kitchen and more storage.
-
2008
Recorded in the city's 2008 survey of the Transit Center District, adopted in 2012, as a contributor to the proposed New Montgomery, Mission & Second Historic District.
-
Dec 2010
Relocation of salad and hot food bar, installation of counter, soda machines, soda fountain machine.
-
Apr 2011
Remodel (build) existing restaurant/deli on the ground floor to include new bathroom, partitions, counters, electrical and upgrade the front door accessibility. storefront under seperate permit.
-
Jun 2011
Relocate pendents off existing system, relocating 19 heads. most work in mezzanine ceiling, some on 1st floor.
-
Apr 2012
5th floor/suite #500 - demolition & construct new floors, lights, painting & a few partitions are to be installed. this space is currently unoccupied. t-24, m.e.p under seperate permit.
-
Feb 2013
Main lobby only. demoliton & replacement of a main lobby store front system as a required ada upgrade. maher ordinance not applicable, disturbance is less than 50 cu yd of soil.
-
Mar 2013
6th fl: demolition of existing doors, partitions, ceiling, lighting, electrical tel/data receptacles, conduit and cabling and finishes throughout one floor of a 7 story building. nw construction of nw partitions, doors, ceiling & lighting, electrical, tel/data receptacles, conduit & cabling, installation of new.
-
Apr 2014
Demolition existing doors partitions, ceiling, lighting, electrical, tel/data receptacles, conduits, cabling & finishes throughout the floor. new construction includes new partitions, doors, ceiling, lighting, electrical, tel/data receptacles, conduit & cabling. new heat pumps under seperate permit.
-
Oct 2014
Selective replacement of kitchen equipment and installation of type 1 hood; maher n/a. ansul & fire alarm deferred submittals.
-
Feb 2015
Provice title 24 certification of compliance, ref #2014.0424.4041. n/a maher ordinance.
-
Oct 2015
Tenant improvement to existing office building, floor 3. demolition existing doors, partitons, ceiling/lighting, electrical finishes. new partitions, doors, ceiling lighting electrical. upgrade e restrooes to comply with add and title 24. new hvac sep permit maher not req.
-
Nov 2016
Ref. 201510028687: ste 300: hvac units for tenant improvement including 3 water source heat pumps, ductwork and thermostatic controls; maher n/a.
-
Aug 2019
Modify entrance of 111 new montgomery to comply with ada access ordinance. maher n/a. no exposed conduit deleted entry system monitiory holes to be patched to match existing substrate new floor to finished concrete.
-
Jan 2020
2nd fl - interior demolition of doors, partitions, ceiling and finishes. new construction to include new partitions, doors, ceilings, lighting. mechanical and electrical work included.
-
Jun 2023
Reroofing.
DBI holds 60 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 60. 3 of them are nominal $1 street-space or sidewalk permits.