140–160 Pine Street

Financial District · San Francisco, CA 94111

  • Office building
  • 7 stories
  • Zoned C3O
  • District 3
  • Historic status: unevaluated
37.7924, −122.3994 Street View appears here once a Google Maps embed key is configured.
96,082 sq ftBuilding area
14,730 sq ftLot area
  1. 1956

    Built.

  2. April 9, 1957

    Photographed, showing the American Fore Building.

  3. Oct 1981

    Additions alterations or repairs.

    Complete Permit 8109018 $$$ $130,000
  4. Mar 1987

    New exterior trim, ground floor windows, doors, lobby.

    Complete Permit 8703568 $$$ $675,000
  5. Apr 1987

    Electrical, door, frames, paint, mechanical.

    Complete Permit 8704704 $$$ $275,000
  6. Apr 1987

    Partitions, electrical, doors, paint, mechanical, frames.

    Complete Permit 8704705 $$$ $264,000
  7. Aug 1988

    Tenant improvements 3rd floor.

    Complete Permit 8810780 $$$ $193,000
  8. Mar 1989

    Cti.

    Complete Permit 8904033 $$$ $275,000
  9. Oct 1992

    Cti-1 2nd floor remove n/b sheetrock partitions.

    Complete Permit 9218764 $$$ $155,302
  10. Dec 1995

    Cti-1 floor 3rd el me sp.

    Complete Permit 9520986 $$$ $191,000
  11. Mar 1996

    Cti-1 5thfl, el, me, sp.

    Complete Permit 9604162 $$$ $157,200
  12. May 2001

    Oti-1, 3rd floor, ltg, mechanical, ls & spr.

    Expired Permit 200105088612 $$$ $120,000
  13. May 2003

    Retail t.i., path of travel & ada restroom upgrade, fire alarm/sprinkler under seperate permit.

    Complete Permit 200305094262 $$$ $210,000
  14. Jul 2006

    Oti-1 4th floor el me ls sp.

    Complete Permit 200607075906 $$$ $150,000
  15. Aug 2006

    Oti-2 4th floor el.

    Complete Permit 200608230292 $$$ $114,000
  16. Dec 2013

    6th floor - office tenant improvement of approx 3, 855 gross sq ft to include the addition of new non-structural partitions, finishes & millwork upgrades. sprinkler/fire life safety, mechanical & electrical drawings are deferred.

    Complete Permit 201312234925 $$$ $300,000
  17. Dec 2014

    1st floor: remodeling existing dental office, minor t.i. and modification of ceiling and wall; maher n/a.

    Complete Permit 201412042997 $$$ $293,375
  18. Feb 2015

    #140b - change of occupancy from vacant retail to a quick service restaurant (1173 s.f.). n/a maher ordinance (ti build out of existing "m" 1173sf vacant space at main floor of existing building to a quick service restaurant - chahnge of occupancy; no exterior modifications).

    Complete Permit 201502138389 $$$ $120,000
  19. Aug 2018

    7/f: demolition of select non-structural partitions, new non-structural partitions, doors, millwork on 7th floor only. mep-life safety-sprinklers under seperate permit.

    Complete Permit 201808248228 $$$ $183,000
  20. Sep 2018

    2nd floor: suite 250 t.i. includes demolition of non structural partitions and build new non str partitions. all new or revised. mep, life safety and sprinklers under seperate permit. n/a for maher.

    Complete Permit 201809180604 $$$ $734,000
  21. Sep 2018

    5th floor: suite 510: t.i. includes demolition of non structural partitions and build new non str partitions. all new or revised. mep, life safety and sprinklers under seperate permit. n/a for maher.

    Complete Permit 201809180601 $$$ $646,000
  22. Nov 2018

    Demolition and relocate duct and quipment as shown. install new duct and equipment as shown. install new lighting and outlets throughout suite ref 201809180604.

    Cancelled Permit 201811065144 $$$ $320,000
  23. Nov 2018

    Demolition low pressure ductwork per plans. install low pressure ductwork. install new exhaust fan. install new lighting and power ref 201809180601.

    Complete Permit 201811065147 $$$ $190,000
  24. Sep 2019

    Suite 350 - ti demolition of non structural partitions and bld new non structural partitions. mep/fire/life safety under seperat permit.

    Complete Permit 201909050689 $$$ $890,000
  25. Oct 2019

    Ste 350 - modification of existing hvac systems. new power and data for work station & offices. new break room. new lighting & controls ref pa 2019-0905-0689.

    Complete Permit 201910285720 $$$ $451,202
  26. Mar 2026

    7/f-ste 710. ti include the demolition fo non structural partition and building non-structural partitions. all new or revised meps and life safety work will be design build and submitted for permit separtely. building is fully sprinklerd.

    Issued Permit 202603117357 $$$ $650,000

DBI holds 150 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 150. 2 of them are nominal $1 street-space or sidewalk permits.