3150 18th Street
Mission · San Francisco, CA 94110
-
Jun 1985
Tie-into existing system & add new sprinkler.
-
Mar 1990
Phase i work only, roof bracing per plans.
-
Nov 1994
Phase #2 work per plan phase #1 ref. permit application 9003947.
-
Aug 1999
Special procedures (seismic upgrade) roof anchors.
-
Oct 1999
New wall partitions, new carpet, new storefront for barrier.
-
Mar 2000
Street space.
-
May 2000
Install fire alarm to monitor water flow.
-
Nov 2000
Tenant improvement, add 2 sprinkler hds & relocate 2 hds(2nd floor).
-
Dec 2000
Install fire alarm to monitor waterflow, renew app#200005099468.
-
Apr 2001
Duct modifications & new zoning in office area & mezzanine are.
-
May 2004
To erect a new 5 story mixed use building (workspaces, retail, 1 residental, parking).
-
Dec 2006
To install fire sprinkler system.
-
May 2007
Build out of new space - kitchen, interior finishes for cafe change of use b1 to a-3. add 2 hr glazing. existing permit appl for new building 200405214487.
-
Aug 2007
Fire sprinkler alarm monitoring system and elevator recall. comploaint #200669688.
-
Aug 2007
Revision (as-built) of project -sprinkler system. sprinkler main size reduced to 2 1/2" calculation revised. plans revised are sheets fs-6 and fs-7 only. this is revision to permit #2004/05/21/4487 s4.
-
Sep 2007
Install approx. 28 feet of 6" underground pipe (pvc class 150).
-
2008
Built as an apartment building.
-
Jun 2008
Design retail space and a portion of the space (25%) will be used as an espresso bar by adding sink & counter.
-
Dec 2014
2' drywall repairs due to flood. new vinyl flooring. repair work only, no structural work, no wall modification. n/a ordinance #155-13.
-
May 2017
Change of use from office to personal use tattoo-permanent cosmetics, no work.
-
Dec 2019
Change of use of (14) worshops from f-1 to b (massage facilities) pursuant to planning code sec 192. note: change of use and/or occupancy shall comply with 2016 cbc, chapter-5.
-
Dec 2019
Change of use of 5, 000 sq ft from f-1 to b (health service). note: change of use and/or occupancy shall comply with 2016 cbc, chapter-5.
-
May 2020
The work outlined in these plans is related to the repairs of vent holes through fire rated assemblies and shear plywood to allow for moisture due to water damage to vent out. all repair work will be complete to return the commercial building to original conditions including installation of plywood.
-
Feb 2025
To abate nov 202317343 by patching leak & repair sheet rock.not visable from street. 5sf of sheetrock repair.
-
Aug 2025
Reroofing. torch down.
DBI holds 43 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 43. 5 of them are nominal $1 street-space or sidewalk permits.
Not yet documented: the year the building went up, the architect and builder, the early tenants and the date of the last recorded sale. Submit an update