101 Mission Street
South Beach · San Francisco, CA 94105
-
1976
The three-storey brick warehouse then on the corner was given an architectural rating of "0" and a summary rating of "1" in the city's 1976 architectural survey. It was typical of what was built south of Market Street early in the twentieth century, and one of the last two- and three-storey brick buildings left on the block.
-
1981
The brick building on the corner had been pulled down by late 1981, after the City Planning Commission approved a twenty-storey tower for the site in August of that year.
-
Mar 1982
New construction.
-
Mar 1984
Construction of drywall glass partitions acoustical hvac.
-
1985
Built.
-
Dec 2000
Oti-1 2nd floor, el, me, ls, sp.
-
May 2006
New life safety system upgrade for fire building. this system to replace existing system.
-
Apr 2010
Lobby renovation, new flooring, ceiling, wood features. mep included. demolition work under separate permit. fire sprinklers & fire alarm under separate permit.
-
Dec 2015
8th floor: ti with demolition, new walls, millwork, ceiling, electrical, plumbing and hvac. maher na.
-
Mar 2017
12th floor: selective demolition of existing finishes in a vacant unoccupied full floor suite. t.i. including construction of non-rated of nonstructural partitions, new glazing, doors, new ceiling & lighting fixtures, nw electrical & tel/data, nw millwork & sinks, new finishes throughout, accessibility.
-
Aug 2017
#800 8/f- minor renovations to existing tenant space. #920 9/f- full tenant fit-out including demolition existing interior walls, plumbing and millwork. new interior walls, doors, new finishes and furniture. n/a ordinance #155-13.
-
Oct 2018
5th floor: interior t.i. to 5th floor office space.new offices and break area. n/a for maher.
-
Oct 2018
Ste 320 - partial floor ti existing non-rated demising wall to remain. demolition of existing interior partitions, ceiling/wall/floor finishes construction of new non-load bearing partitions and interior finishes. mep deferred.
-
Dec 2018
Tenant improvement on 17th fl to construct new walls/partitions, doors, glazing, millwork, ceiling, and finishes. mep systesm and fire prevention to be pulled under separate permits. maher n/a.
-
Feb 2019
18th fl: ti of existing unoccupied full floor suite 1800. selective interior non-structural demolition, new non-structural partitions, d/f/h, finishes, millwork, ceiling, lighting. no chnage in occup/use or area. acessibility upgrade at mens & women's rr. mep under seperate permit.
-
Apr 2019
20th fl. t.i. of existing unoccupied full tenant fl. no change in occupancy, use, or area. accessible restroom, demolition, drinking under sep permit n/a maher.
-
Jul 2019
21th floor - spec suite ti of existing unoccupied suite.. no change in occupancy, use or area. accessible restrooms & drinking fountation under sep permit.
-
Oct 2019
Suite 200: interior tenant improvement combining 2 unoccupied tenant suites into full floor speculative office suite. suite will remain unoccupied at project completion.
-
Dec 2019
3rd fl: full floor spec suite ti at existing unoccupied multi-tenant floor. the floor will remain unoccupied at the completion of this project. no chang ein use or area. maher na.
-
Jul 2020
Partial t.i for 21/f including only mechanical/electrical/plumbing, no structural.
-
Jul 2020
Partial t.i for 20/f including only mechanical/electrical/plumbing, no structural.
-
Jul 2020
Office t.i.; minor structural, small kitchen, removal of non structural partitions, acoustical ceilings, architectural finishes and casework.
-
Mar 2023
Ste# 450 - spec suite t.i. of existing unoccupied suite on a multi-tenant floor. no change in occupancy, use or area.
-
May 2023
Tenant improvement combining 2 existing unoccupied suites on a multi-tenant floor. no change in occupancy, use or area.
-
Sep 2023
16th fl: lighting only for t.i. (office) ref permit application 2023-0914-6547.
-
May 2026
19/fl- ti to include non structrual partitions, doors, lighting, ceilings, and finishes. renovated restrooms, additional single user restroom and renovated elevator lobbies. mep deferred.
-
Jul 2026
19/f: mep submittal to support approved arch permit. new vav boxes, exhaust fans, lighting, and power throughout. ref: #202605271978.
DBI holds 781 permits for this parcel, most of them tenant improvements on individual floors. The timeline shows the 24 largest by stated cost, plus the earliest on file; the DBI query in the sources below returns all 781. 3 of them are nominal $1 street-space or sidewalk permits.
Nearby
- 1 Mission Street Same street
- 123 Mission Street Same street
- 150 Spear Street Same block
- 115–135 Main Street Same block
- 160 Spear Street Same block
- 180–182 Howard Street Same block